APPENDIX A
()
NOTICE OF VIOLATION Philadelphia Electric Company Docket No. 50-352 This refers to the inspection conducted by a representative of the Region I (Philadelphia) office at the Limerick Generating Station, Unit 1, Limerick, Pennsylvanis, of activities authorized by NRC License No. CPPR-106.
During this inspection conducted on Feb. 25 - Mar. 25, 1980, the following apparent item of noncompliance was identified:
Appendix B, of 10 CFR 50, Criterion V, states in part:
" Activities affecting quality... shall be accomplished in accordance with these instructions, procedures or drawings...".
The Limerick PSAR, Appendix D, Quality Assurance Program, Paragraph D.6.4 states, in part, that:
Bechtel Construction Department...is responsible for construction of the plant to approved engineering specifications, drawings, and procedures...".
Bechtel Power Corporation welding standard "GWS-Structural" Revision 2, states in Section 5.1 that the minimum preheat temperature of 700F for a weld joint thickness range of 3/4" - 1 " shall be maintained during all welding.
Contrary to the above, on March 3,.1980 a welder was about to weld on pipe restraint (PR-239) without preheating the weld joint. The temperature in the working area was in the low sixties. This item is a deficiency.