ML19320B627

From kanterella
Jump to navigation Jump to search
Part 21 Rept Re Deficiencies of Cutler-Hammer Motor Control Ctrs.Cause Undetermined.Proposes That Starter Units W/ Improper Wire Be Returned to Manufacturer for Rewiring & That Splice Plate Carriage Bolts Be Replaced
ML19320B627
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 06/25/1980
From: Davidson D
CLEVELAND ELECTRIC ILLUMINATING CO.
To:
References
REF-PT21-80-223-001 NUDOCS 8007140534
Download: ML19320B627 (2)


Text

niinuu o novu u m uuinuiauuuuuu.

..w.

ss s u n

$Ibt c_h,

~ ' PART 21 IDBfTIFICATION NO. 36-J-2 3-oo / C0ffANf IME IMTE OF ETIER

%s'/Fe, DOCKET NO. ft,fo-Wo IWIE DISTRIBilTED 7/ 7/ # o ORIGINALREPORT SUPPLEfBTARY X DISTRIBllTION:

~~

REACTOR (R) [

FUELCYCLE&

SAFEGUARDS (S)

VATERIALS (M)

.IE FILES IE FIES AD/RDI (2)

IE FILES AD / SG AD/RCI AD / FRSI AD / ROI REGIONS EGIONS REGIONS VSIDOR BR. R IV VBiDOR BR. R IV VENDOR BR R IV L0EB / IPA MiB 5715 NFES / FCFS NRR / DDR AEOD tTiB7602 L0EB / IPA MiB5715 Ni'SS / SG SS-881 NRR / DDR (2)

AEOD MiB7602 LOEB / IPA nib 5715 NRR / DPM (2)

CENTRAL FILES 016 AEOD nib 7602 CENTRAL FILES 016 CENTRAL FIES (CHRON)

CBITRAL FIES 016 CENTRAL FIES (GRON)

PDR CBITRAL FIES (GRO.O PDR LPDR CENIFAL FIES SS -39~

LPDR TERA PDR TERA LPDR TERA ACTION:

' PRELIMINARY EVALUATION OF THE ATTACHED REPORT It01 CATES LEAD RESPONSIBILITY FOR FOLLOW-UP AS SH0hN BELOW:

IE [

NRR NFSS '[

OTHER[,

IMD ROI SG FFMSI REV.6/L3/80 8 00714o

4 T H E C L E V E !. A N D E C T R I C i L L U :'. i fi> I!!! G lii f

P.o. Box 5000 e CLEVELAND. oHlo M101

'o TELEPHONE (216) 622 9900 e ILLUMINATING BLOG.

e 53 PUBLIC SoUM Da!wyn R. DavidSon viCE PRESPCENT =

SYSTE M ENGINEERING AND CONSTRUCTION June 25, 1980

/[O b

D 4

fo-p 3-oo /

Mr. James G. Keppler Director, Region III Office of Inspection and Enforcement U.S. Nuclear Regulatory Coc=ission 799 Roosevelt Road Glen Ellyn, IL 60137 Re: Perry Nuclear Power Plant Interim Report on Motor-Controlled Centers

Dear Mr. Keppler:

This letter serves as an interim report as required by 10CF'R50.55(e) on the deficiencies concerning Cutler-Hammer motor-control centers. These ite=s were first reported to the NRC by Cutler-Hammer as a 10CFR Part 21 on May 14,1980.

It was later reported as a possible significant deficiency under 10CFR50.55(e) in a' telephone conversation between W. J. Kacer and T. A. Boss of The Cleveland Electric Illuminating Company and Mr. J. Konklin of the URC Region III, Office of Inspection and Enforcement on May 28, 1980.

Description of Deficiency Cutler-Ha==er was contracted by The Cleveland Electric Illuminating Company to manufacture Class lE motor-control centers for Perry Nuc-lear Power Plant. During~ final inspection of a portion of these units, it was discovered that the type SIS wire installed in the switch units

- was not qualified to IEEE 383 and that improper saddle cla ps were used on the terminal blocks. Further inspection of all 1,943 starters revealed that 42 contained' improper wire and 25 contained terminal blocks with improper saddle clamps.

It was later discovered at the job site that four splice plate carriage bolts broke during installa-tion on the bus.

Since these deficiencies place serious doubt on the

. environmental qualification of the equipment, extensive repair will be required to upgrade the units to meet specification requirements.

To meet these requirements, Cutler-Hammer has proposed the following:

v. -

Mr. James G. Keppler June 25, 1980 1.

Return all starter units with-improper wire to the manufac-turer for rewiring.

2.

Replace all ter=inal blocks with improper saddle clamps.

3.. Replace all splice plate carriage bolts.

CEI feels proposals numbers 1 and 2 are adequate to correct their respective deficiencies.

However, we feel that the cause of the carriage bolt breakage has not been adequately addressed.

As a result, we will attempt to determine the cause of the breakage in order to determine the adequacy _of proposal number 3 At the present time CEI is analyzing the broken carriage bolts in an attempt to determine the cause of failure. This evaluation should be completed by July 1, 1980.

After that, a plan to resolve the problem will be coordinated with Cutler-Hammer and a final report on these deficiencies will be submitted by September 30, 1980.

Very truly yours, i

-;/

Dalwyn

. Davidson Vice President System Engineering and Constructicr.