ML19320B033

From kanterella
Jump to navigation Jump to search
Forwards IE Insp Repts 50-440/80-07 & 50-441/80-07 on 800505-07 & Notice of Violation
ML19320B033
Person / Time
Site: Perry  FirstEnergy icon.png
Issue date: 05/21/1980
From: Fiorelli G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Davidson D
CLEVELAND ELECTRIC ILLUMINATING CO.
Shared Package
ML19320B034 List:
References
NUDOCS 8007090154
Download: ML19320B033 (2)


See also: IR 05000440/1980007

Text

--

Ilc

.

terg'

&

o

UN!iED STATES

8'

' 3,

NUCLEAR REGULATORY COMMISSION

$

REGION lli

e'

$ *-

s_ #

o

799 ROOSEVELT ROAD

d

GLEN ELLYN,ILLINots 60137

%#

o

.....

'MAY 21 8801 '

Docket No. 50-440

Docket No. 50-441

The Cleveland Electric Illuminating

Company

ATTN: Dalwyn R. Davidson

Vice President - System

Engineering and Conctruction

Post Office Box 5000

Cleveland, OH 44101

Gentlemen:

This refers to the inspection conducted by Messrs. R. L. Landsman and

E. J. Gallagher of this office on May 5-7, 1980, of activities at the

Perry Nuclear Plant Project, Units 1 and 2, authorized by NRC Construc-

tior. Permits No. CPPR-148 and CPPR-149 and to the discussion of our

findings v"h Wssrs. M. R. Edelman and G. W. Groscup and others of

your sta'

conclusion of the inspection.

The enclosed copy of our inspection report identifies areas examined

during the inspection. Within these areas, the inspection consisted

of a selective examination of procedures and representative records,

observations, and interviews with personnel.

During this inspection, certain of your activities appeared to be in

noncompliance with NRC requirements, as described in the enclosed

Appendix A.

This notice is sent to you pursuant to the provisions of Section 2.201

of the NRC's " Rules of Practice," Part 2, Title 10, Code of Federal

Regulations. Section 2.201 requires you to submit to this office

within thirty days of your receipt of this notice a written statement

or explanation in reply, including for each item of noncompliance:

(1) corrective action taken and the results achieved; (2) corrective

action to be taken to avoid further noncomp'.iance; and (3) the date

when full compliance will be achieved.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part

2, Title 10, Code of Federal Regulations, a copy of this letter, the

enclosures, and your response to this letter will be placed in the

NRC's Public Document Room, except as follows.

If the enclosures con-

tain information that you or your contractors believe to be proprietary,

you must apply in writing to this office, within twenty days of your

receipt of this letter, to withhold such information from public dis-

8 0 0 '7 0 9 o /SY -

r

,

.

The Cleveland Electric

-2-

MAY 21 080

Illuminating Company

closure. The application must include a full statement of the reasons

for which the information is considered propri~etary, and should be

prepared so that proprietary information identified in the application

is contained in an enclosure to the application.

We will gladly discuss any questions you have concerning this inspection.

Sincerely,

N YAL '

2

s ,- _ . - - - -

G. Fiore11i, Chief

Reactor Construction and

Engineering Support Branch

Enclosures:

1.

Appendix A, Notice of

Violation

2.

IE Inspection Reports

No. 50-440/80-07 and

No. 50-441/80-07

cc w/encls:

Central Files

Reproduction Unit NRC 20b

PDR

Local PDR

NSIC

TIC

Harold W. Kohn, Power Siting

Commission

Mr. Daniel D. Wilt, Attorney

-Helen W. Evans, State of Ohio

- -

.

.