Deficiency Rept Re Faulty Connections in Electrical Equipment.As Described in 800201 Deficiency Rept SD 413-414/80-01,all Unit 1 safety-related Motor Control Ctr Equipment Has Been Inspected & Necessary Mods Completed
ML19320A712
Person / Time
Site: Catawba  Duke Energy icon.png
Issue date: 06/18/1980
From: Parker W
DUKE POWER CO.
To:
References
NUDOCS 8007020537
Download: ML19320A712 (1)


Text

.

DUKE POWER COMPJLW

'l Powra Bortntwo 422 SocTa Cacacu StazzT, CiuntoTTz. Njd.'Id$O E E'".. ;

' A N T/,. ; '

.. w w o. n amen,ss..

June 18, 1980

./ %"%

i2 JUU 23 A S :'27 STJU Mr. James P. O'Reilly, Director U. S. Nuclear Regulatory Commission Region II 101 Marietta Street, Suite 3100 Atlanta, Georgia 30303 Re: Catawba Nuclear Station Units 1 and 2 Docket Nos.

50-413 and 50-414

Dear Mr. O'Reilly:

As described in my letter of February 1, 1980, which transmitted Significant Deficiency Report SD 413-414/80-01, all Unit 1 safety-related motor control center equipment furnished by Nelson Electric has been inspected.for proper power wire connections and the necessary modifications completed.

Inspection of Unit 2 safety-related motor control center equipment is sched-uled for completion by December 31, 1980.

Very truly yours, d

William O. Parker, Jr.

RWO:scs cc: Director Office of Inspection and Enforcement U. S. Nuclear Regulatory Commission Washington, D. C.