3 DUKE POWER COMPANY Ld (Octn2a Nuclocr Section, Unito 2 cad 3)
DOCKET NOS. 50-270 AND 50-287
~
ORDER EXTENDING COMPLETION DATES I
Duke Power Company is the holder of Provisional Construction Permits Nos.
CPPR-34 and CPPR-35 issued by the Commission on November 6, 1967, for the construction of the Oconee Nuclear Station, Units 2 and 3, two 2568 megawatt (thermal) pressurized water nuclear reactors presently under construction at the Company's site in Oconee County, South Carolina, approximately eight miles northeast -of Seneca, South Carolina.
On July 3, '1973,' the Company requested an extension of the completion dates because construction of Units 2' and 3 have been delayed due to (1) l diversion of construction forces from Units 2 and 3 to Unit 1 to solve problers occasioned by the lateness of Unit 1, (ii) delay in delivery of major reactor coolant components, and (iii) modifications required to the reactor vessel internals for Unit 2.
The Director of Regulation having determined that this action involves no significaat hazards consideration, and' good cause having been shown, the bases for which are set forth in a memorandum dated July 30, 1973, from R. C. DeYoung to A. Ciambusso:
-IT'IS HEREBY ORDERED THAT the latest completion date for CPPR-34 (Unit 2) is. extended from September 1,1973 to October 1,1973, and the 4
latest completion date for CPPR-35 (Unit 3) is extended from August 1,1973 to June 30, 1974.
FOR THE ATOMIC ENERGY CO.*9 FISSION Criginal signed by QGiambusso A. Giambusso, Deputy Director for Reactor _ Projects Date of' Issuance: JUL 3 0 153 s o 01""Y7E
.