Forwards IE Insp Repts 50-348/80-10 & 50-364/80-11 on 800331-0425.No Noncompliance Noted
ML19318D135
Person / Time
Site: Farley  Southern Nuclear icon.png
Issue date: 06/21/1980
From: Robert Lewis
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Mcdonald R
ALABAMA POWER CO.
Shared Package
ML19318D136 List:
References
NUDOCS 8007070394
Download: ML19318D135 (2)


See also: IR 05000348/1980010

Text

.__ _ _ .___.

.

-__

___ ______.

[b

o# Se

j

UNITED STATES

[pYN

s

y

3,

NUCLEAR REGULATORY COMMISSION

8

E

'E

REGION il

gg

<

o

101 MARIETTA ST,. N.W., SulTE 3100

ATLANTA, GEORGIA 30303

In Reply Refer Tc :

RII:WHB

MAY 2 11980

50-348/80-10

50-364/80-11

Alabama Power Company

ATTN:

R. P. Mcdonald

Vice President-Nuclear Generation

P. O. Box 2641

Birmingham, AL 35291

Gentlemen:

This refers to the inspection conducted by W. H. Bradford of this office on

March 31 through April 25, 1980 of activities authorized by NRC License No.

NPF-2 and Construction Permit No. CPPR-86 for the Farley facility, and to the

discussion of our findings held with W. G. Hairston at the conclusion of the

inspection.

Areas examined during the inspection and our findings are discussed in the

enclosed inspection report. Within these areas, the inspection consisted of

selective examinations of procedures and representative records, interviews with

personnel, and observations by the inspector.

l

Vithin the scope of this inspection, no items of noncompliance were disclosed.

In accordance with Section 2.790 of the NRC's " Rules of Practice", Part 2,

Title 10, Code of Federal Regulations, a copy of this letter and the encloseo

inspection report will be placed in the NRC's Public Document Room.

If this

report contains any information that you (or your contractor) believe to be

proprietary, it is necessary that you make a written application within 20 days

to this office to withhold such information from public disclosure. Any such

application must include a full statement of the reasons on the basis or which

it is claimed that the information is proprietary, and should be prepared so

that proprietary information identified in the application is contained in a

-

separate part of the document.

If we do not hear from you in this regard within

the specified period, the report will be placed in the Public Document Room.

Should you have any questions concerning this letter, we will be glad to discuss

them with you.

Sincerely,

K. c .

.

R. C.

wis, Acting Chief

Reactor Operations and Nuclear -

Support Branch

Enclosures:

Inspection Report Nos. 50-348/80-10

and 50-364/80-11

cc w/ enc 1:

(See Page 2)

800707 0$Tf {

.. -

.

-

- ..

.

Alabama Power Company

-2-

'

B Y 2

t,

,1

cc w/ enc 1:

A. R. Barton

Executive Vice President

P. O. Box 2641

Birmingham, AL 35291

F. L. Clayton, Jr.

Senior Vice President

Post Office Box 2641

Birmingham, AL 35291

H. O. Thrash

Manager-Nuclear Generation

P. O. Box 2641

Birmingham, AL 35291

O. D. Kingsley, Jr.

Manager, Nuclear Engineering and

Technical Services

P. O. Box 2641

Birmingham, AL 35291

J. W. McGowan

Manager-Operations Quality Assurance

P. O. Box 2641

Birmingham, AL 35291

W. G. Hairston, III

Plant Manager

Drawer 470

Ashford, AL 36312

.

yv- et egg - -

  • ' * *