Order to Show Cause Why CP Should Not Be Revoked Since Licensee Intends to Cancel Project
ML19318C247
Person / Time
Site: 05000484
Issue date: 06/16/1980
From: Harold Denton
Office of Nuclear Reactor Regulation
To:
NORTHERN STATES POWER CO.
Shared Package
ML19318C243 List:
References
NUDOCS 8007010263
Download: ML19318C247 (3)


Text

.. ? -n- _ _ _ _ _ _ _ _ _ _ _ _ _

~

UNITED STATES OF AMERICA NUCLEAR REGULATORY CO M ISSION In the Matter of

)

NORTHERN STATES POWER CO., ET AL.

Docket No. STN 50-484 (Tyrone Energy Park, Unit 17- ~

)

ORDER TO SHOW CAUSE I

Northern States Power Company, el al. is the holder of Construction Permit No. CPPR-157 which authorizes the construction of nuclear power reactor Unit 1 at the Tyrone Energy Park in Dunn County, Wisconsin. Construction Pemit No. CPPR-157 was issued on December 27, 1977, and is due to expire on October 1, 1985.

II On July 24, 1979, Northern States Power Co. et al. announced that the co-owners of the proposed facility had voted to cancel the project. By letter dated July 26, 1979, Arthur V. Dienhart, Vice-President of Northern States Power Company informed the Nuclear Regulatory Comission (hereinafter "Comission") of the decision to cancel the project. Mr. Dienhart stated that the co-owners concluded that the " consequences flowing from the denial of the project on March 6,1979, by the Wisconsin Public Service Comission would prevent the project from being placed in service on a schedule required by projected needs for power". He requested the Office of Nuclear Reactor Regulation to teminate further action in this docket.

By letter dated July 25, 1979 Thomas A. Baxter, Esq., Counsel for the Permittees, requested the Atomic Safety and Licensing Appeal Board to tenninate the further proceedings which it had ordered in this docket.7 The Comission has no information to indicate that the Licensees have any intent to renew construction at this

  • / Sy Order dated August 30, 1979, the Appeal Board terminated all proceedings involving the application to license construction of the facility and dismissed the case.

8007010 d63

~

  • facility in the future.

By petition dated August 15, 1979, the Badger Safe Energy Alliance requested the Director of Nuclear Reactor Regulation to institute a proceeding pursuant to 10 CFR 52.202 to revoke the above-described construction permit because of the Licensees' announced decision to cancel the project.

Section 103 of the Atomic Energy Act of 1954, as amended (hcrcinaf ter the Act) authorizes the Commission to issue licenses to. persons who will use utiliza-tion facilities for industrial or commerical purposes and whose proposed activities will serve a useful purpose proportionate to the quantities of special nuclear material or source material to be utilized. - / The pennit issued to Northern States Power Company, et al., pursuant to Section 103, was for the purpose of constructing a utilization facility. Section 186 of the Act provides that "any license may be revoked...because of conditions...which would warrant the Commission to refuse to grant a license on an original application...".

Construction of the Tyrone facility has now been cancelled. The bolders of the. permit issued to authorize its construction no longer propose to conduct activities which will serve a useful commercial purpose within the meaning of the Atomic Energy Act.

III for the reasons set forth in Section II ahove, and pursuant to the Atomic Energy Act of 1954, as anended, and the Commission's regulations in 10 CFR Parts 2 and 50, IT IS HERESY ORDERED THAT:

Northern. States Power Company, et al. show cause, in the mannerhereinafter provided, why construction permit No. CPPR-157 should not be revoked.

  • / 42 U.S.C. 62133(a) & (b).

~~

. IV The Licensee may, within twenty-five (25) days of the date of this Order, file a written answer to this Order under oath or affinnation. The Licensee may consent to the entry of an Order in substantially the form proposed in the Order to Show Cause.

If the Licensee fails to file an answer within the time specified, the Director of Nuclear Reactor Regulation will, without further notice, issue an Order to revoke the Construction Pennit No. CPPR-157. The Licensee or any person whose interest may be affected by this Order may request a hearing within twenty-five (25) days of the date of the Order, setting forth with particularity the interest of the person in the proceeding and how that interest may be affected by the results of the proceeding. Any request for. a hearing shall be addressed to the Director, Office of Nuclear Reactor Regulation, U. S. Nuclear Regulatory Commission, Washington, D. C. 20555, with a copy to the Executive Legal Director at the above address.

If a hearing is requested by a person who has an interest affected by this Order, the Commission will issue an order designating the time an'd place of hearing.

In the event a hearing is requested, the issue to be considered at such hearing shall be:

Whether, on the basis of the Licensee's announced decision to cancel construction of the Tyrone Er.ergy Park, Unit I facility, this Order should be sustained.

FOR THE NUCLEAR REGULATORY CO* MISSION

<s Y

Harold R. Denton, Director Office of Nuclear Reactor Regulation Dated atfethesda, Maryland this l( fyay of June,1980.

.