Forwards Final Deficiency Rept Re Use of Improper Seismic Design Criteria for Design of QA Level I 3/8-inch & 5/8-inch Instrumentation & Control Tubing
ML19318B669
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 06/10/1980
From: Fahrner W
DETROIT EDISON CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
Shared Package
ML19318B670 List:
References
EF2-49-013, EF2-49-13, NUDOCS 8006270282
Download: ML19318B669 (1)


Text

.

v .,

D&q June to. 1980 EF2-49,013 Edison mzw t,e 2 coo second Aven Mr. James C. Keppler Regional Director i

Directorate of Regulatory Operations Region III U.S. Nuclear Regulatory Commission 799 Roosevelt Road Glen "llyn, Illinois 60137 Subj ect: Final Report on 10CFR50.55(e) Item on Seismic Category I Instru-mentation and Control Testing.

Dear Mr. Keppler:

This letter fr submitted as Detroit Edison's final report on the 10CFR50.

55(e) item on the design of Seismic Category I Instrumentation and Control Tubing.

The problem was initially reported on April 14, 1980, in a telephone call f rom Mr. T. A. Alessi and Mr. J.H. Casiglia, of Detroit Edison, to Mr. P.A.

Barrett of NRC Region III. At that time, it was determined that non-seismic design criteria had been used in the design of some QA I Instrumentation and Control Tubing which was required to meet seismic requirements.

Edison Engineering has completed their evaluttion of this deficiency. The attached report includes a description of s .a deficiency, an analysis of the safety implications, and the corrective action taken. Please note that the construction schedule will dictate the priorities for completion of the described action, however, each design will be reviewed and approved to seismic design criteria prior to release for construction.

If you have questions regarding this report or the problem in general, then please contact Mr. H. A. Walker, Supervisor-Construction Quality Assurance.

Sincerely,

I N

, b W.J. Fahrner, Manager Enrico Fermi 2 WJF/ HAW /pn ec: Mr. Victor Stello, Jr., Director Office of Inspection and Enforcement i Division of Reactor Inspection Programs U.S. Nuclear Regulatory Commission O Washington D.C. 20555 3