Forwards IE Insp Rept 50-029/80-07 on 800317-24.No Noncompliance Noted
ML19318B242
Person / Time
Site: Yankee Rowe
Issue date: 05/06/1980
From: Brunner E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Kay J
YANKEE ATOMIC ELECTRIC CO.
Shared Package
ML19318B243 List:
References
NUDOCS 8006250161
Download: ML19318B242 (2)


See also: IR 05000029/1980007

Text

')

-Q

UNITED STATES

[pg y]o

NUCLEAR REGULATORY COMMISSION

[

o

REGION I

$

/ ,, j

$31 PARK AVENUE

?E

KING OF PRUSSIA. PENNSYLVANIA 19406

O

gg g

1990

Docket No. 50-29

Yankee Atomic Electric Company

ATTN: Mr. James A. Kay

Senior Engineer - Licensing

25 Research Drive

~

Westborough, Massachusetts 01581

Gentlemen:

Subject:

Inspection No. 80-07

This refers to the inspection conciucted by Mr. T. Foley of this office

on March 17-24, 1980 at Yankee Nuclear Power Station (Yankee Rowe),

Rowe, Massachusetts of activities authorized by NRC License No. DPR-3

and to the discussions of our findings held by Mr. Foley with Mr. H.

Autio at the conclusion of the inspection, and to a subsequent telephone

discussion between Mr. F. Hicks and Mr. T. Foley on April 15, 1980.

Areas examined during this inspection are described in the Office of

Inspection and Enforcement Inspection Report which is enclosed with this

letter. Within these areas, the inspection consisted of selective

examinations of procedures and representative records, interviews with

personnel, measurements made by the inspector, and observations by the

inspector.

Within the scope of this inspection, no items of noncompliance were

observed.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part

2, Title 10, Code of Federal Regulations, a copy of this letter and the

enclosed inspection report will be placed in the NRC's Public Document

Room.

If this report contains any information that you (or your contractor)

believe to be proprietary, it is necessary that you make a written

application within 20 days to this office to withhold such information

from public disclosure. Any such application must be accompanied by an

affidavit executed by the owner of the information, which identifies the

document or part sought to be withheld, and which contains a statement

l

of reasons which addresses with specificity the items which will be

considered by the Comission as listed in subparagraph (b) (4) of Section

2.790. The information sought to be withheld shall be incorporated as

far as possible into a separate part of the affidavit.

If we do not

l

hear from you in this rega~rd within the specified period, the report

l

will be placed in the Public Document Room.

O

800625 0 W

W

.

.

.

,

WAY 6

1980

Yankee Atomic Electric Company.

2

Should you have any questions concerning this inspection, we will be

pleased to discuss them with you.

Sincerely,

a - - -

Ed

. Brunner, Chief

R ctor Operations and Nuclear

$upport Branch

Enclosure: Office of Inspection and Enforcement Inspection

Report Number 50-29/80-07

cc w/ enc 1:

H. Autio, Plant Superintendent

J. E. Tribble, President

,

l

.

.

-

. - , -

,