Forwards IE Insp Repts 50-373/80-23 & 50-374/80-15 on 800430-0501.No Noncompliance Noted
ML19318A686
Person / Time
Site: LaSalle  
Issue date: 05/16/1980
From: Fiorelli G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Reed C
COMMONWEALTH EDISON CO.
Shared Package
ML19318A687 List:
References
NUDOCS 8006240032
Download: ML19318A686 (2)


See also: IR 05000373/1980023

Text

TIC

Sa teg

[

UNITED STATES

o

'.

8'

'n

NUCLEAR REGULATORY COMMISSION

$

'E

REGION lil

e

799 ROOSEVELT HOAD

d

GLEN ELLYN, ILLINol5 60137

  • ..,*

.

MAY 1 6 1980

.

Docket No. 50-373

Docket No. 50-374

Commonwealth Edison Company

'

ATTN:

Mr. Cordell Reed

Vice President

Post Office Box 767

Chicago, IL 60690

Gentlemen:

This refers to the inspection conducted by Mr. J. H. Neisler of this office

on April 20 - May 1, 1980, of activities at La Salle County Station, Units

1 and 2 authorized by NRC Construction Permit No. CPPR-99 and No. CPPR-100

and to the discussion of our findings with Mr. T. E. Quaka and others of

your staff at the conclusian of the inspection.

The enclosed copy of our inspection report identifies areas examined during

the inspection. Within these areas, the inspection consisted of a selective

examination of procedures and representative records, observations, and in-

terviews with personnel.

'

No items of noncompliance with NRC requirements were identified during the

course of this inspection.

,

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2,

Title 10, C-de of Federal Regulations, a copy of this letter and the en-

closed ir.,2ction report will be placed in the NRC's Public Document Room,

except as follows.

If this report contains information that you or your

contractors believe to be proprietary, you must apply in writing to this

office, within twenty days of your receipt of this letter, to withhold such

information from public disclosure. The application must include a full

statement of the reasons for which the information is considered proprietary,

and should be prepared so that proprietary information identified in the

application is contained in an enclosure to the application.

8 0062 4 ODM

g

. .

,

--

0

Commonwealth Edison Company

-2-

We will gladly discuss any questions you have concerning this

inspection.

.,

Sincerely,

-

G, Fiore111, Chief

Reactor Construction and

Engineering Support Branch

Enclosure:

IE Inspection

Reports No. 50-373/80-23

and No. 50-374/80-15

cc w/ encl:

Mr. D. L. Peoples, Director

of Nuclear Licensing

Mr. L. J. Burke, Site

Project Superintendent

Mr. T. E. Quaka, Quality

Assurance Supervisor

Mr. R. H. Holyoak, Station

Superintendent

Central Files

Reproduction Unit NRC 20b

PDR

Locel PDR

NSIC

TIC

Mr. Dean Hansell, Office of

Assistant Attorney General

1

/