Forwards IE Insp Rept 50-010/80-08 on 800303-05,07,13-14, 0408 & 09 & Notice of Violation
ML19318A433
Person / Time
Site: Dresden 
Issue date: 05/16/1980
From: Davis A
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Reed C
COMMONWEALTH EDISON CO.
Shared Package
ML19318A434 List:
References
NUDOCS 8006230016
Download: ML19318A433 (2)


See also: IR 05000010/1980008

Text

_ _ _ _ _ _ . - _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

/

o.

UNITED STATES

8

%

NUCLEAR REGULATORY COMMISSION

IlC

t

9 :

REGION 111

%

'[

799 ROOSEVELT ROAD

\\

,o

GLEN ELLYN. ILLINOls 60137

D

MAY 16 080

_

~

Docket No. 50-10

Commonwealth Edison Company

ATTN:

Mr. Cordell Reed

Vice President

Post Office Box 767

Chicago, IL 60690

Gentlemen:

This refers to the inspection conducted by Mr. R. A. Paul of this

office on March 3, 4, 5, 7, 13, 14, and April 8, 9, 1980, of activi-

ties at Dresden Nuclear Power Station, Unit 1, authorized by NRC

Operating License No. DPR-2, and to the discussion of our findings

with Mr. Stephenson and other members of your staff at the conclusion

of the inspection.

The enclosed copy of our inspection report identifies areas examined

during the inspection. Within these areas, the inspection consisted

of a selective examination of procedures and representative records,

observations, and interviews with personnel.

During this inspection, certain of your activities appeared to be in

noncompliance with NRC requirements, as described in the enclosed

Appendix A.

This notice is sent to you pursuant to the provisions of Section 2.201

of the NRC's " Rules of Practice," Part 2, Title 10, Code of Federal

Regulations. Section 2.201 requires you to submit to this office within

twenty days of your receipt of this notice a written statement or ex-

planation in reply, including for each item of noncompliance: (1) cor-

rective action taken and the results achieved; (2) corrective action to

be taken to avoid further noncompliance; and (3) the date when full

compliance will be achieved.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part

2, Title 10, Code of Federal Regulations, a copy of this letter, the

~

enclosures, and your response to this letter will be placed in the NRC's

Public Document Room, except as follows.

If the enclosures contain in-

formation that you or your contractors believe to be proprietary, you

must apply in writing to this office, within twenty days of your receipt

of this letter, to withhold such information from public disclosure.

The application must include a full statement of the reasons for which

8006230 4

l

.

Comunonwealth Edison Company

-2-

WAY 16 880'

.

the 'information is considered proprietary, and should be prepared so that

proprietary information identified in the application is contained in an

enclosure to the application.

N will gladly discuss any questions you have concerning this inspection.

Sincerely,

fA"

A. B. Davis, Chief

,

Fuel Facility and

Materials Safety Branch

'

Enclosures:

1.

Appendix A, Notice

of Violation

2.

IE Inspection Report

No. 50-10/30-08

cc w/ enc 1:

.

Mr. D. L. Peoples, Director

of Nuclear Licensing

Mr. B. B. Stephenson,

Station Superintendent

Central Files

Reproduction Unit NRC 20b

PDR

__ Local PDR

NSIC

TIC

Mr. Dean Hansell, Office of

Assistant Attorney General

-