Text
.
DISTRIBUTION:
AEC PDR L al PDR ocket File-NOV 2 3 973 PWR-4 Rdg File Docket No. 50-346 RCDeYoung RWKlecker JHendrie AKenneke The Toledo Edison Company OGC AITN:
Mr. Glenn J. Sampson R0 (3)
Vice President, Pcver IAPeltier HThompson 300 Edison Plaza ASchwencer GKnighton Toledo, Ohio 43652 EGoulbourne JPanzarella Gentlemen:
This letter is in regard to the revision of the schedule for our review of your application for an operating license for your Davis-Besse plant located in Ottawa County, Ohio. We have evaluated our workload in view of the slip in e ustruction completion and current operating license public hearing s, tus, and based on this evaluation, we have re-targeted the issuance of our Final Environmental Statement for May 9, 1975 and our Safety Evaluation Report for April 4, 1975. A summary of the more important milestones as changed are provided as an enclosure to this letter for your information and review. It should be realized that the enclosed dates are target milestones which nay require some changes as the review process proceeds. While we will not formally infor n you (by letter) of minor changes to the schedule, we will confirm, in writing, sistnificant changes to the schedule.
After your review of these milestone changes, please inform us as to vnether or not you believe the dates are realistic.
Sincerely, CnJr -- : 4 k97 S. b:.:
y7 A. Giambusso, Deputy Director for Reactor Projects Directorate of Licensing
Enclosure:
Application Review Schedule T
Y-( h x7548/L_:PWR,-4 L:C/PWR-4 L:A yR
,_ LiDDRP b:C/EP-1 L;EPg1 cmer>
IAPelt
- cjb( ASchw er R e
- ng_,
_AGia usso G
on H
on sumuc >
4 11// /73 11/jt/73, _,,11//]/73
' 11/ 4G3_,
11/lb/73 11/15/73 Form AEC-Ste (Rev. 9 -53) AECM 0240 eco
.aa-to-steaa-a 446-e7s 8 0 01280[$
~
-~
ENCLOSURE APPLICATION REVIEW SCHEDULE PREVIOUS NEW EVENT DATE DATE Starting Point Complete Application, SAR, and ER Docketed 03-31-73 03-31-73 Safety Review Schedule Safety Requests Issued to Applicant 08-03-73 08-28-73*
(first round)
Receive Applicant's Response to Requests 10-12-73 07-05-74 Safety Positions Issued to Applicant 01-04-74 10-04-74 (second round)
Receive Applicant's Response to Positions 03-01-74 12-06-74 Safety Evaluation Report Issued 06-15-74 04-04-75 Supplement to Safety Evaluation Report 08-02-74 08-01-75 I
Issued Environmental Review Schedule Issue Draft Environmental Statement 09-25-73 01-10-75 End Public Comment Period 11-27-73 03-05-75 Receive Applicant's Response to Comments 12-14-73 03-26-75 Issue Final Environmental Statement 01-15-74 05-09-75 Advisory Committee on Reactor Safeguards Advisory Committee on Reactor Safeguards 07-74 05-75 Meeting Receive Advisory Committee on Reactor 07-19-74 05-14-75 Safeguardc Letter
- Complete except for LOCA-ECCS area.
1
\\
,r PREVIOUS NEW EVENT DATE DATE Antitrust Review and Hearing Schedule No hearing reconnended by Attorney General.
No Change Latervention has been requested. AEC decision pending.
Public Hearing Proc:
,.fety and Environmental)
Start Radiological Heat.u; 09-02-74 NS*
End Radiological Hearing 11-01-74 NS*
Start Environ = ental Hearing NS*
NS*
End Environmental Hearing NS*
NS*
End Point Prospective Decision Date 01-06-75 09-01-75
- NS - Not scheduled.
--