Summary of 730521 Telcon W/Util Re Delay of Facility Ascension to 75% Power Until 730609 or 10.Power Mapping Procedure Using Incore Detectors to Be Mailed.Util Committed to Power Mapping at 730515 Meeting Re Fuel Densification
ML19317F014
Person / Time
Site: Oconee Duke Energy icon.png
Issue date: 05/21/1973
From: Peltier I
US ATOMIC ENERGY COMMISSION (AEC)
To:
US ATOMIC ENERGY COMMISSION (AEC)
References
NUDOCS 8001080718
Download: ML19317F014 (1)


Text

i MAY 21 B73 Docket No. 50-269 Note to File TELECON WITH T. COTTON, DUKE POWER COMPANY - OCONEE 1 SCHEDULE - MAY 21, 1973 T. Cotton called to report that Oconee Unit 1 ascention to 75%

power has been delayed to June 9 or 10, 1973 at the earliest. The problem causing the delays at 15% power has been reached Xenon

~

equilibrium because of the many times it has been necessary to go up and down due to trips and turbine problems.

The procedure for power mapping using the incore detectors will be mailed to us within the next few days for our review. Duke committed to power mapping at the fuel densification meeting held here on May 15, 1973.

. D\\ '

e, (y\\i

{

k I. A. Peltier, Proj ect Manager Pressurized Water Reactors Br. No. 4 Directorate of Licensing cc: ASchwencer RCDeYoung HThornburg, RO Dross VStello HSchierling