JAN 2 2 19/.i DocketNos.50h/270/287 NOTE FOR FILES TELECON WITH DUKE POWER COMPANY AND B&W ON ECCS ANALYSIS FOR OTHER THAN FOUR PUMP OPERATION - JANUARY 17, 1973 B&W a tfzed LOCAs for what it considers the worse cases when less than four 1. unps are operating. These were two loop operation with a break in the running loop and a break in the idle loop at 55% power. For the break in the rum..l.ng loop peak clad temperature was 1265'F and for the idle loop was 1305'F.

The next Duke amendment will stated results of analysis and justification for the selection as worse cases.

Participants in the conference call were 1. A. Peltier, D. Davis, T. Novak, K. Canady (Duke), W. O. Parks (B&W).

L I. A. Peltier, Project Manager Pressurized Water Reactors Branch No. 4 Directorate of Licensing cc:

R. C. DeYoung A. Schwencer I

D. Davis T. Novak

)

t)l/

8001070 7//f g

-