Monthly Operating Rept for Oct 1975
ML19317E578
Person / Time
Site: Oconee Duke Energy icon.png
Issue date: 11/06/1975
From: Blakeman E
DUKE POWER CO.
To:
Shared Package
ML19317E577 List:
References
NUDOCS 7912180788
Download: ML19317E578 (3)


Text

.

UntT Oconte 1 DATE 11/6/75 DOCKET NO. 50-269 PREPARED BY E. D. Blakeman OPERATING STATUS

1. REPORTING PERIOD: October 1 IHROUGH October 31, 1975 GROSS HOURS IN REPORTING PERIOD: 745.00
2. CURRENTLY AUTHORIZED POWER LEVEL (MWt): 2568 NET CAPABILITY (MWe-Net): 871
3. POWER LEVEL TO WHICH RESTRICTED (IF ANY):(MWe-Net) None
4. REASONS FOR RESTRICTION (IF ANY)

This Month Year to Date Cumulative

5. NUMBER OF HOURS THE REACTOR WAS CRITICAL 745.0 5540.6 15341.1
6. REACTGR RESERVE SHUTDOWN HOURS
7. HOURS GENERATOR ON-LINE 745.0 5288.0 i3542.3
8. UNIT RESERVE SHUTDOWN HONRS - - -
9. GROSS THERMAL ENERGY GENERATED (MWH)1905505 12698919 30936429
10. GROSS ELECTRICAL ENERGY GENERAirl)

(MWH) 656870 4423800 10742500

11. NET ELECTRICAL ENERGY GENERA 13)

(MWH) 626502 4189086 10142105

12. REACTOR SERVICE FACTOR 100.0 75.9 76.3
13. REACTOR AVAILABILITY FACTOR 100.0 73.1 68.5
14. UNIT SERVICE FACTOR 100.0 72.5 67.3
15. UNIT AVAILABILITY FACTOR 100.0 72.5 67.5
16. UNIT CAPACITY FACTOR (Using Net 96.6 65.9 57.9 Capability)
17. UNIT CAPACITY FACTOR (Using Design Mwe) 94.8 64.7 56.9'

, 18. UNIT FORCED OUTAGE RATE 25.4 17.9

19. SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS (TYPE, DATE & DURATION OF EACH:)

a

20. IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP:

REACTOR SERVICE FACTOR = HOURS REACTOR WAS CRTTICAI. X 100 HOURS IN REPORTING PERIOD REACTOR AVAILABILI'lY FACTOR = HOURS REACTOR UAS_A_V_AILAnt.T' TO OPERATE X 100 Il0URS IN REPORTING PER10J UNIT SERVICE FACTOR = HGITS CD ERATOR ON LT NE y )gg HOURS IN REPORTING PERIOD UNIT AVAILABILITY FACTOR = 110URS UNTT WAS AVATIABLE TO CE*:ERATE X 100 HOURS IN REPORTING PERIOD UNIT CAPACITY FACTOR = NET ELECTRICAL POWER CT.NERATED 1 100

[Not Capability or Denign (Mae-L L).1 X 110UL, 1 R EPnt.Th PtnIm 7 912180 y UNIT FORCED OUTACE RATE - FOR,CED.0UTACE__ HOURS -

X 100 HOURS GENERATOR ON I.INE + FORCED OUTAGE HOURS

DUCKET Np 50-269 UNIT SHUTDOWNS UNIT NAMI Oconee Unit 1 DATl! 11/7/75 REPORT MONTil October TYPE METHOD OF F-FORCED DURATION SHUTTING DOWN NO. DATE S SCHEDULED (HOURS) REASON (1) THE REACTOR (2) CORRECTIVE ACTIONS / COMMENTS ,

(1) REASON (2) METilOD

. A LQUIPMENT l- ALLURE (EMPLAIN) 1-MANUAt B- MAINT. OR TEST. 2-MANUAL C- REI'ULLING SCR AM D-REGULA10RY RtSTRICTION 3-AU10MAllC '

E-OPER ATOR TR AINING AND SCR AM t if t.NSE EXAMINATION F- ADMINIST R AllVE G - OPL R AllON Al. l. R ROR (LXPLAIN)

II-OlllLR (EXPT AIN)

SUMMARY

No outages this month.

50-269 DOCKET NO.

UNIT Oconee 1 DATE 11-7-75 l

AVERAGE DAILY UNIT POWER LEVEL MONTH October,1975 AVERAGE DAILY POWER LEVEL AVERAGE DAILY POWER LEVEL DAY (MWe-net) .

DAY (MWe-net) 841 17 848 1

gg 800 2 846 741 l 846 39 3

788 4 846 20 845 849 5 21 844 850 6 22 848 7 840 -

23 848 848 24 8

842 g 851 25 881

'852 26 10 850 851 27 11 852 12 852 28 852 851 13 29 30 851 l 14 852 l

847 853 31 -

15 16 852 DAILY UNir POWER LEVEL FORM INSTRUCTIONS

' On this form, list the average daily unit power level in MWe-net for each day in the reporting month.

Compute to the nearest whole megawatt.

These figures will be used to plot a graph for each reporting month. Note that by using maximum dependable capacity for the net electrical rating of the unit. there may be occasions when the daily average power level exceeds the 1007c line (or the restricted power level line). In such cases, the average daily unit power output sheet should be footnoted to explain the apparent anomaly.