' INIT Oconce Unit 1 g
0!.IE Sept. 9. 1975 U
DOCKET NO.
50-269 PREPARED BY R. O. Sharpe OPERATING STATUS 1.
REPORTING PERIOD: August 1, 1975 THROUGH August 31. 1975 GROSS HOURS IN REPORTING PERIOD:
744 2.
CURRENTLY AUTHORIZED POWER LEVEL (MWt): 2568 NET CAPABILITY (MWe-Net):
871 3.
POWER LEVEL TO WHICH RESTRICTED (IF ANY):(MWe-Net)
None 4.
REASONS FOR RESTRICTION (IF ANY)
This Month Year to Date Cumulative 5.
NUMBER OF HOURS THE REACTOR WAS CRITICAL 728.2 4075.6 13876.1 6.
REACTOR RESERVE SHUTDOWN HOURS 7.
HOURS GENERATOR ON-LINE 695.9 3823.0 12077.3 8.
UNIT RESERVE SHUTDOWN HOURS 9.
-GROSS THERMAL ENERGY GENERATED (sm) 1689758 8952232 27189742 10.
GROSS ELECTRICAL ENERGY GENERATED (EH) 584870 3135140 9453840 11.
NET ELECTRICAL ENERGY GENERATED (MWH) 555008 2960127 8913146 12.
REACTOR SERVICE FACTOR 97.9 69.9 74.4 13.
REACTOR AVAILABILITY FACTOR 94.6 66.3 66.0 14.
UNIT SERVICE FACTOR 93.5 65.6 64.8 15.
UNIT AVAILABILITY FACTOR 93.5 65.6 64.9 16.
UNIT CAPACITY FACTOR (Using Net 85.7 58.3 54.9 Capability) 17.
UNIT CAPACITY FACTOR (Using Design Mwe) 84.1 57.2 53.9 18.
UNIT FORCED OUTAGE RATE 3.9 32.0 19.7 19.
SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS (TYPE, DATE & DURATION OF EACH:)
Refueling, February 1976 20.
IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP:
REACTOR SERVICE FACTOR = HOURS REACTOR WAS CRITTCA?. X 100 Il0VRS IN REror. TING PEl.10D REACTOR AVAllABILI'IY FACTOR = 110t!PS REACT 01: UAS AVATIAhLE TO OPERATE X MO
!!0U1.5 1!; RLronTiriG l'E!i10D UNIT SERVICE TACTO::
= 110t':S CE;;p' /. TOR O'; 1.1 NE
!!Ol!RS ):: RI.'POK11r;G PEl:10D ". y gg y
UNIT AVAIL \\BTLITY FACTOR
- liot'RS UNIT WAS AVA11 Ah!.E TO_ GE!!ERATE X 100 llOURS iii REl'URTING l'ERIOD UNIT CAI'ACITY FACT 0H
= NE T E1.ECTRI CAL POWER _C;ENER'.TED.
( N.. t Cai'.La i l i t ) or Desis.n (L e-Net'y, a 1; AUK.s IN HUNr li.,100 v
.m 79121807 73 pen mD UNIT FORCED OUTACE RA1E e TOP.CfD OUTAGE I!OPMS X 100 110VRS GENDL*.Trn ON 1.1140 -'- FORCED OUTN;F !!OURS l
D CKET NO. 50-269 UNIT SHUTDOWNS UNIT NAME Oconee Unit 1 DATE Sept. 9, 1975 REPORT MONTil _ August, 1975 TtPE METHOD OF F FORCED DURATION SHUTTING 00WN NO.
DATE S-SCHEDULED (HOURS)
RE ASON (1)
THE REACTOR (2)
CORRECTIVE ACTIONS / COMMENTS 12 750801 S
20.03-B 1
Continuation of 750726 outage 13 750802 F
7.35 B
3 Failure of stator cooling pressure switch 14 750808 F
7.62 B
3 Unit trip while testing turbine valves 15 750809 F
13.08 H
3 Trip due to flux imbalance on restart
- L (I) REASON (2) METIIOD A. EQUIPMENT FAILURE IEXPLAIN) l-MANtfAL I
B-MAINT. OR TEST.
2-MANUAL C-RLI UE LING SCR AM D-REGULAlORY RESTRICTION 3 - AUTOM ATIC E-OPFRATOR TRAINING AND SCR AM l.101 NSE EXAMINAllON F-A DMINIS T R AllVE G - Ol'l R AllON Al. l'R ROR (1.X P LAIN) 11-OlllL R II.XPLAIN)
SUMMARY
No ciajor outages during August.
1 DOCKET NO. 50-269 UNIT oconee Unit _1 DATE Sept. 9, 1975 AVERAGE DAILY UNIT POWER LEVEL MONTH August, 1975 AVERAGE DAILY POWER LEVEL AVERAGE DAILY POWER LEVEL DAY (MWe-net)
DAY (MWe-net) 6 1
17 844 2
344 18 R4?
746 19 845 3
778 20 844 4
5 21 842 819 6
22 838 820 7
818 23 832 8
510 24 843 9
120 25 843
'720 26 844 10 11 748 27 RLA 12 788 28 848 s
13 824 29 842 14 30 837 828 810 31 842 15 16 816 DAILY UNIT PO$ER LEVEL FORM INSTRUCTIONS On this form, list the average daily unit power level in MWe-net for each day in the reportin ; month.
Compute to the nearest whole megawatt.
These figures will be used to plot a graph for each reporting month. Note that by usin! maximum i
dependable capacity for the net electrical ratmg of the unit. there_may be neasions when the daily average power level exceeds the IOO'!i line (or the restricted power level hnet in such cases, the average daily unit power output sheet should be footnoted to explain the app.nent anomaly.