Order Extending CPPR-34 Const Completion Date from 731001 to 731104
ML19316A678
Person / Time
Site: Oconee 
Issue date: 09/24/1973
From: Anthony Giambusso
US ATOMIC ENERGY COMMISSION (AEC)
To:
DUKE POWER CO.
Shared Package
ML19316A645 List:
References
NUDOCS 8001130228
Download: ML19316A678 (1)


Text

i

(

(

DUKE POUER CO:iP/d;Y I

(Oconee Nuclear Strition, Unit 2) of DOCKET NO. 50-270 ORDER EXTENDING COMPLETION DATE Duke Power Company is the holder of Provisional Construction Permit No. CPPR-34 issued by the Commission on November 6,1967, for the con-ntruction of the Oconee Nuclear Station, Unit 2, a 2568 megawatt (thernal) pressurized water nuclear reactor prerently under construction at the Company's site in Oconee County, South Carolina, approximately eight niles northeast of Seneca, South Carolina.

l On August 29, 1973, the Company requested an extension of the com-I pletion date because construction of Unit 2 has been delayed due to (1) diversion of construction forces from Unit 2 to Unit 1 to solve prob.'aras occasioned by the lateness of Unit 1, (2) delay in delivery of major reactor coolant components, and (3) modifications required to the reactor vessel internals for Unit 2.

The Director of Regulation having determined that this action involves no significant hazards consideration, and good cause having been shown, the bases for which are set forth in a nemorandum dated September 21, 1973, from R. C. De"oung to A. Giambusso*

IT IS HERFM ORDERED THAT the latest completion date for CPPR-34 (Unit 2) is extended from October 1,1973 to November 4,1973.

FOR THE ATOMIC ENERGY CO}C4ISSION Original Si'ned by A. Giambusso A. Giambusso, Deputy Director for Reactor Projects Directorate of Licensing Date of Issuance: