Order Extending CPPR-34 Completion Date Until 730901
ML19316A663
Person / Time
Site: Oconee 
Issue date: 02/28/1973
From: Anthony Giambusso
US ATOMIC ENERGY COMMISSION (AEC)
To:
US ATOMIC ENERGY COMMISSION (AEC)
Shared Package
ML19316A660 List:
References
NUDOCS 8001130213
Download: ML19316A663 (1)


Text

..

DitKEQPO'.s'ER COMPANY (Oconee Nuclear Station, Unit 2)

DOCKET NO. 50-270 ORDER EXTENDING COMPLETION DATE Duke Power Company is the holder of Provisional Construction Permit No. CPPR-34 issued by the Coamission on November 6, 1967, for the construction of the Oconee Nucicar Station, Unit 2, a 2568 megawatt (thermal) pressurized water nucicar reactor presently under construction at the Company's site in Oconce County, South Carolina, approximately eight miles northeast of Seneca, South Carolina.

On January 25, 1973, the Con.pany requested an extension of the com-pletion date because construction of Unit 2 has been delayed due to (1) diversion of construction forces from Unit 2 to Unit 1 to solve problems occasioned by the lateness of Unit 1, (ii) delay in delivery of major reactor coolant components, and (iii) modifications required to the reactor vessel internals for Unit 2.

' Die Director of Regulation having determined that this action involves no significant hazards consideration, and good cause having been shown:

.IT IS HEREBY ORDERED THAT the latest completion date for CPPR-34 is extended' f rom February 28, 1973, to September 1, 1973.

FOR THE ATOMIC ENERGY COMMISSION Original ?'ed by

.' DarnLusco A. Ciambusso, Deputy Director for Reactor Projects Directorate of Licensing Date of Issuance: FES 2 01973 GfS I!