O n'uxz Powrn COMPANY Powru Butz.orwo 422 Socin Caracu Srazzr, CnAntorTr. N. C. asa4a wl L Ll A he Q. PA R M E R, J R, ViCs Pe Sieg.et Tetspi o=c:Anta 704 Sega Pecouctio.
37 3.so a s May 31, 1977 Mr. Norman C. Moseley, Director U. S. Nuclear Regulatory Commission Suite 818 230 Peachtree Street, Northwest Atlanta, Georgia 30303 Re:
IE:II:CEA 50-269/77-4 50-270/77-4 50-287/77-4
Dear Mr. Moseley:
With regard t-) your letter of May 6, 1977, Duke Power Company does not consider information contained in IE Inspection Report 50-269,
-270, -287/77-4 to be proprietary.
Please find attached our response to Item I.
Ver truly yours, N
W. a O.
William O. Parker, Jr.
LJB:vr Attachment t
.g 912 050 i
I._l
]
i RESPONSE TO IE INSPECTION REPORT 50-269, -270, -287/77-4 Item I Contrary to the requirements of Paragraph 50.54(1-1) of 10 CFR 50, the licensee failed to implement an operator requalification program meeting the minimum requirements of Appendix A to 10 CFR 55, in that as of April 7, 1977, systematic reactor operator performance evaluations had not been completed, documented and reviewed as specified in Sections 5 and 6 of the licensee's approved requalification program.
RESPONSE
A program is being established at Oconee Nuclear Station which will assure proper evaluation, documentation, and review of the performance of non-supervisory licensed operators.
This program will be implemented by July 1, 1977.
'}*
,