Forwards IE Insp Rept 50-458/80-04 on 800331-0403. No Noncompliance Noted
ML19312E092
Person / Time
Site: River Bend 
Issue date: 04/16/1980
From: Seidle W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Weigand J
GULF STATES UTILITIES CO.
Shared Package
ML19312E093 List:
References
NUDOCS 8006030218
Download: ML19312E092 (2)


See also: IR 05000458/1980004

Text

. _ _ _ _ _ _ _ _ _ _ - _ _ _

. _ . ._

/SC

UNITED STATES

/em "80w%g

NUCLEAR REGULATORY COMMISSION

,

.7 V

/

REGloN IV

'

n

I

ii#!(

c

611 RYAN PLAZA DRIVE, SUITE 1000

j

ARLINGTON, TEXAS 76012

% g.

.,

sr

g

April 16, 1980

.

In Reply Refer To:

RIV

Docket No. 50-458/Rpt. 80-04

i

Gulf States Utilities

ATTN:

Dr. J. G. Weigand, Vice President

Operations and Technical Systems

Post Office Box 2951

Beaumont, Texas

77704

Gentlemen:

.

This refers to the inspection conducted by Mr. A. B. Beach of our staff during

the period March 31 - April 3, 1980, of activities authorized by NRC Construction

Permit No. CPPR-145 for River Bend, Unit No. 1, and to the discussion of our

j

findings with Mr. T. L. Crouse and other members of your staff at the

conclusion of the inspection.

Areas examined during the inspection and our findings are discussed in the

enclosed inspection report. Within these areas, the inspection consisted

of selective examination of procedures and representative records, interviews

1

with personnel, and observations by the inspector.

Within the scope of the inspection, no items of noncompliance were identified.

One new unresolved item is identified in paragraph 2 of the enclosed report.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2,

Title 10, Code of Federal Regulations, a copy of this letter and the enclosed

inspection report will be placed in the NRC's Public Document Room.

If the

report contains any information that you believe to be proprietary, it is

necessary that you submit a written application to this office, within 20 days

of the date of this letter, requesting that such information be withheld from

public disclosure. The application must include a full statement of the reasons

why it is claimed that the information is proprietary.

The application should

be prepared so that any proprietary information identified is contained in an

enclosure to the application, since the application without the enclosure will

also be placed in the Public Document Room.

If we do not hear from you in this

regard within the specified period, the report will be placed in the Public

Document Room.

8 00603 0#th

)

. -

-

. .

.

Gulf States Utilities

-2-

April 16, 1980

Should you have any questions concerning this inspection, we will be pleased

to discuss them with you.

,

Sincerely,

.

. C. Seidle, Chief

Reactor Construction and

,

Engineering Support Branch

Enclosure:

IE Inspection Repor' No. 50-458/80-04