DISTRIBUTION I. A. Peltier FEB 2 1973 R. C. DeYoung A. Schwencer Docket flo. (g70 fiOTE TO FILE OCONEE U:{IT 2 SCllEDULE DELAY
\\
\\
On January 26, 1973 Ken Canady of Duke informed me that the new
\\
schedule for Unit 2 is as follows.
\\\\
}
Start flFT June 1,1973 Start Fuel Loading August 1,1973 s
Initial Criticality August 7,1973 Begin Power Escalation Septer.ber 7, 1973
\\
100% Power fiovember 7,1973 Connercial Operation December 1, 1973
{v The basis for the delay in fuel loading from May 15,1973 was i
\\
given as modifications to the plant resulting from Oconee 1
\\
experiences.
I. A. Peltier, Project Manager Pressurized Water Reactors Branch fio. 4 Directorate of Licensing J