Forwards Interim Deficiency Rept 3 Re post-tensioning Anchorhead Failure.Requests Extension Until 800630 for Submittal of Final Rept
ML19309H942
Person / Time
Site: Byron  Constellation icon.png
Issue date: 05/15/1980
From: Naughton W
COMMONWEALTH EDISON CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
Shared Package
ML19309H943 List:
References
NUDOCS 8005200689
Download: ML19309H942 (1)


Text

9 M-; Comm:nwn!!h Edison

. [ $a ons First TJarrona: F*aza. Cpcago. lihoois 8G()52 00fvqo.7 Q y' Addr:sa Reply to: Post Cfhec Box 767

. Chicago, Illir1ois 60690 May 15, 1980 Mr. James G. Keppler, Director Directorate of Inspection and.

Enforcement,- Region III U.S. Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, IL e0137

Subject:

Byron Station Units 1 and 2 Post-Tensioning Anchornead Failure NRC Docket Nos. 50-454 and 50 455_

Reference (a): December 26, 1979 letter from V:. F.

'Naughton to J. G. Keppler (b): February 29, 1980 letter from W. F. Naughton to J. G. Keppler

Dear Mr. Keppler:

Commonwealth Edison Company notified your office en November 29, 1979 of the failure of two (2) field anchorheads for the horizontal tendens used to post-tension the concrete (primary) containment on Byron Units 1 and 2. That notification was made under 10 CFR 50.55(e). References (a) and (b) contained interim reports concerning these failures, as well as two (2) additional failures. As indicated in the attached third interim report, testing has not yet reached a point where conclusive results are available to resolve this ceficiency. Final resolution is now scheduled for June 30, 1980. The re fore , Commonwealth Edison requests an extension to that time for submittal of the final report.

Pl' ease address any questions you may have to this office. _

Very truly yot.rs,

. A W. F. Naughion Nuclear Licensing Administrator Pressurized ?later Reactors Attachment cc: -Director of Inspection J

%\

Enforcement 2112

-,