Commonwealth Edison one First Natioral Ptaza. C?ucago. Ilknots Address Reply to: Post Office Box 767 Chicago, Illinois 60690 February 29, 1980 Mr. James G. Keppler, Director Directorate of Inspection and Enforcement - Region III U.S. Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, IL 60137
Subject:
Byron Station Units 1 and 2 Post-Tensioning Anchorhead Failure NRC Docket Nos. 50-454 and 50-455 Reference (a): December 26, 1979 letter from W. F.
Naughton to J. G. Keppler Oear Mr. Keppler:
Commonwealth Edison Company notified your office on November 29,'1979 of the failure of two (2) field anchorheads for the horizontal tendons used to post-tension the concrete (primary) containment on Byron Units 1 and 2.
That notification was made under 10 CFR 50.55(e).
Reference (a) contained an interim report concerning these failures.
As indicated in the attached second interim report, additional failures have occurred necessitating further testing to resolve this deficiency.
Final resolution is now scheduled for May 15, 1980.
Therefore, Commonwealth Edison requests an extension to that time for submittal of the final report.
Please address any questions you may have to this office.
Very truly yours, k
W. F. Nau ton Nuclear Licensing Administrator Pressurized Water Reactors Attachment cc: