Responds to IE Bulletin 79-01B.Actions Required by Items 4 & 5 Can Be Completed by 800630.Responses Required by Items 1,2 & 3 Will Be Submitted by 800421
ML19309E501
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 04/17/1980
From: Richard Bright
FLORIDA POWER CORP.
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
IEB-79-01B, IEB-79-1B, NUDOCS 8004220526
Download: ML19309E501 (2)


Text

.

Florida Power coa pon a r <og April 17, 1980 Mr. J. P. O'Reilly Director Office of Inspection and Enforcement U.S. Nuclear Regulatory Commission Suite 3100 101 Marietta Street Atlanta, GA 30303

Subject:

Crystal River Unit 3 Docket No. 50-302 Operating License flo. DPR-72 IE Bulletin 79-018 - ENVIRCNMEf4TAL QUALIFICATIGft 0F CLASS IE EQUIPMEf1T

Dear Mr. O'Reilly:

We have completely reviewed the scope of IE Bulletin 79-01B as requested and have determined that the actions required by Items 4 and 5 can be com-pleted by June 30, 1980.

The responses, as required by Items 1, 2 and 3, are on schedule and will be submitted to you by April 21, 1980 as was indi-cated in our March 6, 1980 letter.

We have estimated that 1600 manhours or 40 manweeks are required to con-plete this response. Approximately 700 manhours have been expended to date which mostly involved the actions required by Items 1, 2 and 3.

Some of the problems encountered that prevent meeting the schedule outlined in the Bulletin include the following:

1.

Time consuming searches of in-house files to locate and compare environmental data and documentation for all equipment included in the scope of the Bulletin.

2.

The many contacts required with vendors in cases where in-house data is incomplete (particularly for equipment located outside containment).

3.

Developing the service condition profiles for all of the equip-ment identified.

O l

General Of tice roi inmovm snee sw. p o n. uce st Pe enesa 'cua 33n3. e13 -:M 5 5' 8 00422 0 (2[2

d Mr. J. P. 0'Reilly Page Two April 17,1980 4.

Overall amount of detail involved for the respanses.

Should you have any questions concerning this-response, please contact this office.

Very truly yours, FLORIDA POWER CORPORATION

/b__)([

,- - 7,

R. M. Bright Acting Manager Nuclear Support Services RMBemhWO6047 cc: Director Office of Inspection and Enforcement Division of Reactor Operations Inspection U.S.. Nuclear Regulatnry Connission Washington, D.C. 20555 File: