ML19309E444

From kanterella
Jump to navigation Jump to search
Forwards IE Bulletin 80-08, Exam of Containment Liner Penetration Welds. Written Response Required
ML19309E444
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 04/09/1980
From: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Crouse R
TOLEDO EDISON CO.
References
NUDOCS 8004220057
Download: ML19309E444 (1)


Text

[

'o UNITED STATES Tl0 8'

F, NUCLEAR REGULATORY COMMISSION i

1 j

{

.rE REGION 111 b[

799 ROOSEVELT ROAD o,

o GLEN ELLYN,ILLINolS 60137 Docket No. 50-346 APR8 1980 Toledo Edison Company ATTN:

Mr. Richard P. Crouse i

Vice President Nuclear Edison Plaza 300 Madison Avenue Toledo, OH 43652 Gentlemen:

The enclosed Bulletin 80-08 is forwarded to you for action. A

/

written response is required.

If you desire additional information regarding this matter, please contact this office.

Sincerely, n

James G. Keppler Director

Enclosure:

IE Bulletin No. 80-08 i

cc w/ encl:

Mr. T. Murray, Station Superintendent Central Files l

Director, NRR/DPM Director, NRR/ DOR PDR Local PDR NSIC TIC Harold W. Kohn, Power Siting Commission Helen W. Evans, State of Ohio l

2 8004220pg f

SSINS No.: 6820 UNITED STATES Accessions No.:

i NUCLEAR REGULATORY COMMISSION 7912190650 0FFICE OF INSPECTION AND ENFDD.CCMENi WASHINGTON, D.C.

20555 April 7, 1980 IE Bulletin No. 80-08 EXAMINATION OF CONTAINMENT LINER PENETRATION WELDS Description of Circumstances:

On March 20-23, 1!79, an NRC inspection at Nine d ie Point Unit 2, identified that certain nondestructive examinations performed on containment penetration welds did not satisfy the applicable ASME Boiler and Pre m ra Vessel (B&PV)

Code requirements. The welds in question were the primary piping containment penetration flued head (integral fitting) to outer sleeve welds which form a part of the containment pressure boundary. The examinations performed included ultrasonic and surface inspections of the outer surface.

S wsequent to the identification ot this code problem at Nine Mile Point Unit 2, three welds previously found to be acceptable using ultrasonics were radio-graphed and two revealed indications in excess of the code allowable.

The indications revealed by radiography were slag and lack-of-fusion.

Preliminary NRC review indicates that the probable reason the indications were not detected by ultrasonics was due to masking from signals received from the backing bar.

As 3 result of these findings, a complete re-examination program at Nine Mile Point Unit 2 was initiated wherein 10 of 17 welds previously examined and found to be acceptable using ultrasonics, were re-examined by radiography before rework and found to have indications exceeding ASME Code allowables.

Additional information concerning Beaver Valley Unit 2 and North Anna 3 and 4 has also shown cases of flued head piping penetration weld defects exceeding ASME B&PV Code acceptance criteria when radiographed.

Original approved vendor procedures at Beaver Valley Unit 2 did not require volumetric examina-tion.

Radiography for information purposes disclosed the unacceptable indica-tions at North Anna 3 and 4. Specification deficiencies have also been discovered at Millstone 3 and River Bend where radiography of these welds was not required.

The ASME B&PV Code requires radiography of the subject welds with specified exceptions. The licensees and their architect engineer (Stone and Webster) had specified ultrasonics as the volumetric examination method because, in their judgement, radiography was impractical for the penetration geometry.

Radiography was successfully performed at North Anna 3 and 4 prior to the identification of this problem and at Beaver Valley 2 and Nine Mile Point 2 subsequent to NRC inspections.

This experience indicates that radiography was meaningful and more practical than UT examination of these penetration welds i

when backing bars are present.

l

+c

-.o.

..se-m.--,,e

--w<

.c

~

IE Bulletin No. 80-08 April 7, 1980

.}

Page 2 of 2 Action to be Taken by Lice w:

For all power reactor feilities with an operating license or a cotstruction permit:

1.-

Determine if your facility contains the flued head design for penetration connections, or other cesigns with containment boundary butt weld (s) between the penetration sleeve and process piping as illustrated in Figure NE 1120-1, Winter 1975 Addenda to the 1974 and later editions of the ASME B&F/ Code.

2.

If an affirmative answer is reached for Item 1, determine the following:

a.

Applicability of the ASME Code including year and addenda and/or Regulatory Guide 1.19, b.

Type of nondestructive examinations performed during construction, c.

Type of weld joint (including pipe material and size) and whether or noi. hacking bars were used, d.

Results of construction nondestructive examinations, i.e., if repairs were required, this should be identified including extent of l

repairs and description of defects encountered during repair, if known.

3.

For those facilities committed during construction to perform volumetric examination of such penetrations through SAR commitments which have not performed radiography, justify not performing radiography or submit plans and schedules for performing radiographic examinations.

Within 90 days of the date of this Bulletin, facilities with an operating license or a construction permit shall submit the information requested in Items 1, 2, and 3 of this Bulletin.

Reports shall be submitted to the Regional Director with a copy to the Director, Division of Reactor Construction Inspection, Washington, D. C.

20555.

Approved by GAO, B180225 (R0072); clearance expires 7-37.-80.

Approval was given under a blanket clearance specifically for ident'fied generic problems.

t l

l

'~1

!'~~

. ~~

t IE Bulletin No. 80-08 Enclosure

,l April 7, 1980 RECENTLY ISSUED IE BULLETINS Bulletin Subject Date Issued Issued-To (l

No.

'. *h 80-07 BWR Jet Pump Assembly 4/4/80 All GE BWR-3 and Failure BWR-4 facilities with an OL 80-06 Engineered Safety Feature 3/13/80 All power reactor (ESF) Reset Controls facilities with an OL 80-05 Vacuum Condition Resulting 3/10/80 All PWR power reactor In Damage To Chemical Volume facilities holding Control System (CVCS) Holdup OLs and to those with Tanks a CP 79-01B Environmental Qualification 2/29/80 A11 power reactor of Class IE Equipment facilities with an OL 80-04 Analysis of a PWR Main 2/8/80 All PWR reactor facilities Steam Line Break With holding OLs and to those Continued Feedwater nearing licensing Addition 80-03 Loss of Charcoal From 2/6/80 All holders of Power Standard Type II, 2 Inch, Reactor OLs and cps Tray Adsorber Cells l

80-02 Inadequate Quality 1/21/80 All BWR licenses with

)

Assurance for Nuclear a CP or OL 80-01 Operability of ADS Valve 1/11/80 All BWR power reactor Pneumatic Supply facilities with and i

OL 79-018 Environmental Qualification 1/14/80 All power reactor of Class IE Equipment facilities with an OL l

79-28 Possible Malfunction of 12/7/79 All power reactor Namco Model EA 180 Limit facilities with an Switches at Elevated OL or a CP Temperatures i

.~ -

... - -.:,. : : *~~. C..

l.

i

  • ~