ML19309E199

From kanterella
Jump to navigation Jump to search
Forwards IE Insp Rept 50-423/80-01 on 800213-15.No Noncompliance Noted
ML19309E199
Person / Time
Site: Millstone Dominion icon.png
Issue date: 03/06/1980
From: Robert Carlson
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Counsil W
NORTHEAST NUCLEAR ENERGY CO.
Shared Package
ML19309E200 List:
References
NUDOCS 8004210003
Download: ML19309E199 (2)


See also: IR 05000423/1980001

Text

g -.

[h

-

, gg

UNITED STATES

jo

NUCLEAR REGULATORY COMMisslON

y

o

REGION I

$

$

63'1 P AR K AVENUE

'f

KING OF PRUSSI A, PENNSYLV ANI A 19406

.....

HA2 061918

Docket No. 50-423

Northeast Nuclear Energy Company

ATTN: Mr. W. G. Counsil

Vice President - Nuclear

Engineering and Operations

,

P. O. Box 270

Hartford, Connecticut 06101

.

Gentlemen:

Subject:

Inspection Report No. 50-423/80-01

This refers to the inspection conducted by Mr. A. Cerne of this office

on February 13-15, 1980 at the Millstone Nuclear Power Station, Unit 3,

at Waterford, Connecticut of activities authorized by NRC License No.

CPPR-113 and to the discussions of our findings held by Mr. Cerne with

Mr. S. Toth and others of your staff at the conclusion of the inspection.

Areas examined during this inspection are described in the Office of

Inspection and Enforcement Inspection Report which is enclosed with this

letter. Within these areas, the inspection consisted of selective

examinations of procedures and representative records, interviews with

personnel, and observations by the inspector.

Within the scope of this inspection, no items of noncompliance were

observed.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part

2, Title 10, Code of Federal Regulations, a copy of this letter and the

enclosed inspection report will be placed in the NRC's Public Document

.

Room.

If this report contains any information that you (or your contractor)

believe to be proprietary, it is necessary that you make a written

application within 20 days to this office to withhold such information

from public disclosure.

Any such application must be accompanied by an

affidavit executed by the owner of the information, which identifies the

document or part sought to be withheld, and which contains a statement

!

of reasons which addresses with specificity the items which will be

considered by the Commission as listed in subparagraph (b) (4) of Section

2.790.

The information sought to be withheld shall be incorporated as

far as possible into a separate part of the affidavit.

If we do not

!

hear from you in this regard within the specified period, the report

'

will be placed in the Public Document Room.

i

8 0 04 210 ooS

,

.

.

Northeast Nuclear Energy Company

2

No reply to this letter is required; however, should you have any questions

'

concerning this inspection, we will be pleased to discuss them with you.

Sincerely,

f

4=- _

-

Robert T. Carlson, Chief

,

Reactor Construction and Engineering

i

Support Branch

Enclosure:

Office of Inspection and Enforcement Inspection

Report No.

50-423/80-01

7

cc w/ encl:

K. W. Gray, Construction Quality Assurance Lead

,

H. R. Nims, Director of Nuclear Projects

'

J. F. Opeka, Station Superintendent

J. R. Himmelwright, Licensing Safeguards Engineer

,

l

!

l

.

.

-

- - - - -