V2-Jersey Central Power & IJght Company
.q LI.
(4~ (
J Madison Avenue at Punch Bow! Road Morristown, New Jersey o7960 (201)455-8200 February 22, 1980 Mr. Boyce H. Grier, Director Office of Inspection and Enforcement Region I 631 Park Avenue King of Prussia, PA 19406
Dear Mr. Grier:
Subject:
Oyster Creek Nuclear Generating Station Docket No. 50-219 IE Bulletin No. 79-27 The purpose of this letter is to advise you of our schedule to complete the required actions identified in IE Bulletin 79-27.
Because of the scope of this bulletin and its manpower requirements, we are unable to complete a response to this bulletin within the required 90 days, which expire on February 28, 1980. We, therefore, request an extension until April 25, 1980.
We presently have three contract engineers (Stone & Webster) and one Jersey i
Central Power & Light engineer assigned to complete this task.
Specific detailed I&C load assignments to each bus are being tabulated (60% complete) to complete the evaluation.
The status of the response, by item, is as follows:
Iteml Percent Complete Remarks 1.
a),b).c) 0%
Load identification in progress.
2.
a),b),c) 25%
Emergency procedures for loss of power were reviewed.
Must be compared with results of item 1.b.
3.
75%
None.
Jery truly yours, g~A Donald A. Ross, Manager Generating Stations-Nuclear bj cc: