Notifies That NRC Initial Review of Util 790904 Safeguards Contingency Plan Complete.Requests Addl Info within 30 Days in Order to Complete Review.Info Request Withheld (Ref 10CFR2.790)
ML19309B213
Person / Time
Site: North Anna 
Issue date: 02/27/1980
From: Schwencer A
Office of Nuclear Reactor Regulation
To: Ferguson J
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
References
NUDOCS 8004030276
Download: ML19309B213 (2)


Text

{

/b ca cla

,;r..

,0, UNITED STATES y j i s. / [,g NUCLEAR REGULATORY COMMISSION j.C WASHINGTON, D. C. 20555 February 27, 1980

+....

Docket No. 50-338 Mr. J. H. Ferguson Executive Vice President - Power Virginia Electric and Power Company Post Office Box 26666 Richmond, Virginia 23261

Dear fir. Ferguson:

SUBJECT:

NORTH ANNA P0tlER STATION SAFEGUARDS CONTINGENCY PLAN We have completed our initial review of the Safeguards Contingency Plan (SCP) revision submitted by you on September 4,1979 for the North Anna Power Station.

In order that we may continue our review of your SCP, additional information is required. The information requested is provided in the enclosure to this letter.

!!e request that your response to the enclosure be submitted within 30. days.. ___.

receipt of this letter.

Please inform us within 7 days after receipt of this letter of your confirmation of our requested response date or the date you will be able to meet.

The enclosure which contains information of a type specified in 10 CFR 2.790 is being withheld from public disclosure, Sincerely, h.

ayudv A. Schwencer, Chief Operating Reactors Branch #1 Division of Operating Reactors

Enclosure:

Corments on Safeguards Contingency Plan, North Anna Power Station Attachment to be Withheld from Public Disclosure g(r04030 2.7f