Notice of Violation from Insp on 800115-18
ML19309B194
Person / Time
Site: Prairie Island 
Issue date: 02/13/1980
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML19309B193 List:
References
50-306-80-03, 50-306-80-3, NUDOCS 8004030252
Download: ML19309B194 (1)


Text

-

O Appendix A NOTICE OF VIOLATION Northern States Power Company Docket No. 50-306 Based on the results of an ERC inspection conducted on January 15-18, 1980, it appears that certain of your activities were not conducted in full compliance with NRC requirements, as noted below.

This item is an infrac-tion.

~

Technical Specification 4.2.A.4 states in part, that, nondestructive in-spections listed in Table TS 4.2-1, shall be performed as specified.

Northern States Power (NSP) Procedure No. NSP-PT-1, Revision 1, Section F-1 states, " Penetrant manufactures corresponding developer, as listed in Figure 1, shall be applied by spraying immediately af ter the penetrant removal and drying operation has been completed." This procedure requires a (5) minute drying time.

ASME Section V, Article 6, Subarticle T-646 states, "The developer shall be applied as soon as possible after penetrant removal.

Contrary to the above, the inspector observed on January 17, 1980, during a liquid penetrant examination of Pressurizer Nozzles No. 156/2 and No.

164/2, line No. 6-2RC-20A and No. 6-2RC-20B, NAVC0 Drawing No. A7636(8),

that developer had not been applied af ter penetrant removal until approxi-mately 30 minutes on one nozzle and over ten minutes on the other nozzle.