Forwards IE Insp Repts 50-321/79-33,50-366/79-37, 50-424/79-16 & 50-425/79-16 on 791105-06,08 & 13 & Notice of Violation
ML19308C687
Person / Time
Site: Hatch, Vogtle  Southern Nuclear icon.png
Issue date: 11/26/1979
From: Murphy C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: John Miller
GEORGIA POWER CO.
Shared Package
ML19308C679 List:
References
NUDOCS 8002010118
Download: ML19308C687 (2)


See also: IR 05000321/1979033

Text

O

\\'n

-

UNITED STATES

8

NUCLEAR REGULATORY COMMISSION

g'

$

-

E

REGION ll

o,

[

101 MARIETTA ST., N.W., SUITE 3100

.....[

ATLANTA, GEORGIA 30303

NOV 2 61979

In Reply Refer To:

RII:VLB

50-321/79-33

50-366/79-37

50-424/79-16

50-425/79-16

.

Georgia Power Company

ATTN:

J. H. Miller, Jr.

'

Executive Vice President

270 Peachtree Street

Atlanta, GA 30303

Gentlemen:

This refers to the inspection conducted by V. L. Brownlee of this office on

November 5, 6, 8, and 13, 1979, of activities authorized by NRC Operating License

No. DPR-57, License No. NPF-5, and Construction Permit Nos. CPPR-108 and CPPR-109

,

for the E. I. Hatch Nuclear plants and Vogtle Nuclear facility, and to the discus-

sion of our findings held with W. A. Widener on November 6,1979 and R. W. Staffa

on November 13, 1979, at the conclusion of the inspection.

Areas examined during the inspection and our findings are du. cussed in the

enclosed inspection report.

Within these areas, the inspection consisted of

selective examinations of procedures and representative records, interviews with

personnel, and observations by the inspectors.

During the inspection, it was found that certain activities under your license

appear to be in noncompliance with NRC requirements. This item and references

to pertinent requirements are listed in the Notice of Violation enclosed herewith

as Appendix A.

This notice is sent. to you pursuant to the provisions of Section

2.201 of the NRC's " Rules of Pract. ice," Part 2, Title 10, Code of Federal Regula-

tions. Section 2.201 requires you to submit to this office, within 20 days of

your receipt of this notice, a written statement or explanation in reply including:

(1) corrective steps which have been taken by you and the results achieved; (2)

corrective steps which will be taken to avoid further noncompliance; and (3) the

date when full compliance will be achieved.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2, Title

10, Code of Federal Regulations, a copy of this letter and the enclosed inspection

report will be placed in the NRC's Public Document Room. If this report contains

any information that you (or your contractor) believe to be proprietary, it is

necessary that you make a written application within 20 days to this office to

withhold such information from public disclosure. Any such application must

include a full statement of the reasons on the basis of which it is claimed that

the information is proprieta ry, and should be prepared so that proprietary

information identified in the application is contained in a separate part of the

document. If we do not hear from you in this regard within the specified period,

the report will be placed in the Public Document Room.

8002010N

-

L

.~

.

.

NOV 2 61979

Georgia Power Company

-2-

i

Should you have any questions concerning this letter, we will be glad to discuss

them with you,

t

Sincerely,

N"f

.

C. E. Murphy,' CiIib'f

Reactor Construction and Engineering

,

j

Support Branch

Enclosures:

1.

Appendix A, Notice of Violation

2.

Inspection Report Nos. 50-321/79-33,

50-366/79-37, 50-424/79-16 and 50-425/79-16

cc w/ encl:

i

M. Manry, Plant Manager

P. O. Box 442

Baxley, GA 31513

,

C. E. Belflower

'

.

Site QA Supervisor

P. O. Box 442

Baxley, GA 31513

W. A. Widner

Manager-Nuclear Operations

Georgia Power Company

'

Post Office Box 4545

-

Atlanta, Georgia 30303

K. M. Gillespie,

'

Construction Project Manager

P. O. Box 282

Waynesboro, GA 30830

E. D. Groover

QA Site Supervisor

,

P. O. Box 282

Waynesboro, GA 30830

'

D. E. Dutton

Project General Manager

Georgia Power Company

'

Post Office Box 4545

'

Atlanta, Georgia 30303

,

'

.

l'

,

,

.-

, . ~ .

-

-

-

-

.