ML19308A731
| ML19308A731 | |
| Person / Time | |
|---|---|
| Site: | Oconee |
| Issue date: | 02/14/1975 |
| From: | Thies A DUKE POWER CO. |
| To: | Moseley N NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
| References | |
| NUDOCS 7912100613 | |
| Download: ML19308A731 (2) | |
Text
_.
[
.)
J Letter to H. C. Moseley from Duke Power Company dated February 14, 1975 i
DISTFIEUTIott:
50-269 H. D. Thornburg, E IS:EQS (5)
Office of Standanis Development
? Central F$2.es l
Division of Reactor Licensing (13)
PDR Local PDR NSIC TIC STATE 1
l
\\
.G nisteo 4/3 3
1
- 4e
A)
DUKE power COMPANY Powrn Buttanto 422 SouTu Cnunen SrazzT, CHAntorTz, N. C. asaos A. C. *nt a ss P. O. Box 217e sa.o. v.cc P=s.iec.e ou..... r........
February 14, 1975 Mr. Norman C. Moseley, Director U. S. Nuclear Regulat.ary Commission Suite 818 230 Peachtree Street, Northwest Atlanta, Georgia 30303 Re: Oconee Unit 1 Docket No. 50-269 Dear M*
Moseley:
1 Unusual Event Report UE-269/74-6 reported a ficiency in the seismic qualification of the control rod drive system AC breaker cabinets at Oconee Nuclear Station.
The report stated that a modification was being prepared to increase the attachment strength of the cabinet to the floor.
This modification was to be completed by February 1, 1975.
i A design review of the modification proposed by B&W has indicated that the modification cannot be accomplished due to close interferenc2 of l
nearby equipment.
Consequently, the modification is being re-avaluated and a proposed design change should be available by March 1, 1975.
Modification of the trip breaker cabinets must be performed during a unit. outage. Therefore, modification of the cabinets will be performed during the first scheduled unit outage following review and approval of the design change.
Very truly yours, kM4 A. C. Thies ACT:vr
~
.