Forwards IE Insp Repts 50-445/80-04 & 50-446/80-04 on 800211-15. No Noncompliance Noted
ML19305E057
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 02/29/1980
From: Seidle W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Gary J
TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC)
Shared Package
ML19305E058 List:
References
NUDOCS 8004220232
Download: ML19305E057 (2)


See also: IR 05000445/1980004

Text

0

D

,-

. q

3~

~3

T '_ E . - h ;i 3 ' .

79 E h CI.1I 'l 3.$ 12 '

G C<n:

F)

NP.4ADPRE S ATE 1c;?

Ar.LIN G TO!. . T E X A5 762%

February 29, 1980

.....

In Reply Refer To:

RIV

Docket No.

50-445/Rpt 80-04

50-446/Rpt 80-04

Texas Utilities Generating Company

ATTN: Mr. R. J. Gary, Executive Vice

President and General Manager

,

2001 Bryan Tower

Dallas, Texas 75201

Gentlemen:

This refers to the inspection conducted by R. H. Brickley of our staff

on February 11-15, 1980, of activities authorized by NRC Construction

,

Permits No. CPPR-126 and 127 for the Comanche Peak facility, Units No.1

and 2, and to the discussion of our findings with Mr. R. G. Tolson and

other members of your staff at the conclusion of the inspection.

'

Areas examined during the inspection and our findings are discussed in the

enclosed inspection report. Within these areas, the inspection consisted

of selective examination of procedures and representative records, inter-

views with personnel, and observations by the inspector.

r

Within the scope of the inspection, no items of noncompliance were identi-

fied.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2,

Title 10, Code of Federal Regulations, a copy of this letter and the

enclosed inspection report will be placed in the NRC's Public Document

Room.

If the report contains any information that you believe to be pro-

prietary. it is necessary that you submit a written application to this

office, within 20 days of the date of this letter, requesting that such

information be withheld from public disclosure.

The application must

include a full statement of the reasons why it is claimed that the informa-

tion is proprietary. The application should be prepared so that any

proprietary information identified is contained in an enclosure to the

application, since the application without the enclosure will also be

placed in the Public Document Room.

If we do not hear from you in this

regard within the specified period, the report will be placed in the

Public Document Room.

I

l

8004220232

l

<

.

.

Texcs Utilities Gensrst.ing Company

2

February 29, 1980

Should you have any questions concerning this inspection, we will be pleased

to discuss them with you.

Sincerely,

.

'

/

lf_/ /

  • ds-

,

W. C. Seidih Chief

l

Reactor Construction and

Engineering Support Branch

,

Enclosure:

i

IE Inspection Report No. 50-445/80-04

.

50-446/80-04

cc: w/ enclosure

!

Texas Utilities Generating Company

ATIN:

Mr. H. C. Schmidt, Project Manager

2001 Bryan Tower

Dallas, Texas

75201

!

.

>