Forwards IE Info Notice 80-14, Safety Suggestions from Employees. No Action Required
ML19305E027
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 04/02/1980
From: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Burstein S
WISCONSIN ELECTRIC POWER CO.
References
NUDOCS 8004220158
Download: ML19305E027 (1)


Text

,-

CENTRAL FILES 4

\\

APR 2 ng Docket No. 50-266 Docket No. 50-301 Wisconsin Electric Power Company ATTN:

Mr. Sol Burstein Executive Vice President Power Plants 231 West Michigan Milwaukee, WI 53201 Gentlemen:

The enclosed Information Notice provides information regarding the practices to be followed by NRC inspectors when they receive expressions of concern related to safety from plant employees.

Sincerely, James G. Keppler Director

Enclosure:

IE Information Notice No. 80-14 cc w/ encl:

Mr. G. A. Reed, Plant Manager Central Files Director, NRR/DPM Director, NRR/ DOR C. M. Trammell, ORB /NRR PDR Local PDR NSIC TIC Sandra A. Bast, Lakeshore Citizens for Safe Energy Mr. John J. Duffy, Chief Boiler Inspector, Department of Industry, Labor and Human Relations RIII RII Heis an/km K@pler 4/2/80 8004220 fff

.\\

1 SSINS No.: 6870 UNITED STATES Accession No.:

\\

NUCLEAR REGULATORY COMMISSION 8002280649 I

0FFICE OF INSPECTION AND ENFORCEMENT WASHINGTON, D.C.

20555 April 2, 1980 IE Information Notice No. 80-14 SAFETY SUGGESTIONS FROM EMPLOYEES On February 29, 1980, the NRC Office of Inspection and Enforcement issued an instruction to NRC inspectors on the handling of safety suggestions received from licensee employees during inspections.

A copy of the instruction, Temporary Instruction No. 1210/1, is enclosed.

The purpose of this instruction is to reaffirm to inspectors that they must be sensitive to the safety concerns of employees. We encourage employees to attempt resolution of their safety concerns through the normal communication channels to their supervisors and managers.

Nevertheless, there are instances where an employee apparently feels more comfortable expressing his or her safety concerns to an NRC inspector.

In these cases, the inspector will follow the practices described in the enclo,ed instruction.

We suggest that licensees post this Inforration Notice and the enclosed instruction in an area where employees c;.n read them.

Enclosure:

IE Temporary Instruction No. 1210/1 i

l l

l

[

_...a,_....-a-_.,1 T ' ' ~ ".

-s

N TI 1210/1 Issue Date: 2/29/80

.g SAFETY SUGGESTIONS RECEIVED DURING INSPECTIONS During inspections, inspectors may receive safety suggestions relating to plant conditions or operations from licensee employees.

Inspectors must be receptive to such suggestions and should attempt to resolve or deal with each one received.

Even in those cases where the suggestion would require a licensee to do more than is required by NRC regulations, license conditions, or technical specifications, the inspector should discuss the suggestion with the employee and provide, to the best of the inspector's ability, the options that are available.

Depending upon the nature of the suggestion, some possible courses of action are as follows:

1.

Encourage the employee to forward the suggestion in writing to plant managemt.nt and, if appropriate, to the NRC.

2.

For matters clearly under the jurisdiction of another Federal agency, or a state or local agency, encourage the employee to contact the appropriate agency, or offer to bring the'information to the attention of the proper official.

3.

Inform the employee that the matter will be evaluated and, if appropriate, brought to the attention of NRC management.

It is important that an employee profferring a suggestion related to safety be made aware that the NRC is interested in such suggestions and they will be pursued. r~r -

.~ -.

~*

~

~'

5 IE Infcrmation Notica No. 80-14 Enclosure April 2, 1980 RECENTLY ISSUED i

IE INFORMATION NOTICES Information Subject Date Issued To Notice No.

Issued 80-13 General Electric Type SBM 4/2/80 All light water reactor Control Swiches - Defective facilities holding power Cam Followers reactor OLs or cps 80-12 Instrument Failure Causes 3/31/80 All holders of power Opening of PORV and Block reactor OLs and cps Valve 80-11 General Problems with ASCO 3/14/80 All holders of Reactor Valves in Nuclear Application OL, CP, fuel fabrica-Including Fire Protection tion and processing Systems facilities 80-10 Partial Loss of Non-Nuclear 3/7/80 All power reactor Instrument System Power facilities holding Supply During Operation OLs and cps 80-09 Possible Occupational 3/7/80 All holders of Health Hazard Associated power reactor OLs with Closed Cooling Systems and near term cps 80-08 The States Company Sliding 3/7/80 All power reactor Link Electrical Terminal facilities with an OL Block or a CP 80-07 Pump Shaft Fatigue Cracking 2/29/80 All Light Water Reactor Facilities holder power reactor OLs and cps l

80-06 Notification of Significant 2/27/80 All holders of Reactor Events OLs and to near term OL applicants i

80-05 Chloride Contamination 2/8/80 All licensees of nuclear

+

of Safety Related Piping power reactor facilities and applicants and holders of nuclear power i

reactor cps 80-04 BWR Fuel Exposure in 2/4/80 All BWR's holding a Excess of Limits power reactor OL or CP w.__.

.,r.

.