ML19305C592

From kanterella
Jump to navigation Jump to search
IE Insp Rept 50-358/79-37 on 791227-28 & 800117-28. Noncompliance Noted:Failure to Execute Piping Suspension Sys Activities & to Control Work Procedures.Inadequate Measures Taken to Protect Hydraulic Snubbers from Damage
ML19305C592
Person / Time
Site: Zimmer
Issue date: 02/12/1980
From: Danielson D, Yin I
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML19305C588 List:
References
50-358-79-37, NUDOCS 8003310124
Download: ML19305C592 (8)


See also: IR 05000358/1979037

Text

.

U.S. NUCLEAR REGULATORY COMMISSION

.

OFFICE OF INSPECTION AND ENFORCEMENT

REGION III

Report No. 50-358/79-37

Docket No. 50-358

License No. CPPR-88

Licensee:

Cincinnati Gas and Electric Company

139 East 4th Street

Cincinnati, OH 45201

Facility Name:

Wm. H. Zimmer Power Station

Inr.pection At:

Zimmer Site, Moscow, Ohio

Inspection Conducted. December 27-28, 1979, and January 17-18, 1980

.DYllt.

Inspector:

I. T. Yin

-

' 2 } E'

r~

Accompanying Personnel:

G. Fiorelli

(January 18, 1980, only) R. C. Knop

T. E. Vandel

17htG J rJ k ~

1

1 I

Approved By:

D. H. Danielson, Chief

*/ ' 2/

,C

Engineering Support Section 2

Inspection Summary

Inspection on December 27-28, 1979 and January 17-18, 1980 (Report No.

50-358/79-37)

Areas Inspected:

Inspection of safety related hanger, restraint, and

snubber site inspection program. The inspection involved a total of 18

inspector-hours onsite by one NRC inspector.

Results:

In the one area inspected, four apparent items of noncompliance

were identified (infraction-failure to execute piping suspension system

activities

paragraph 2; infraction-failure to control work procedures -

paragraph 3; infraction-inadequate measures to protect hydraulic snubbers

from damage

paragraph 4; infraction-failure to promptly identify defici-

encies and prevent their reoccurrence - paragraph 5.)

8003810IQg

.

.__-.

_

. _ -

-

-_.

.

DETAILS

.

Persons Contacted

Site Inspection on December 27-28, 1979 and January 17, 1980

f

Principal Licensee (CG & E) Personnel

  • B. K. Culver, Project Manager

W. W. Schwiers, QA Manager

  • J. F. Weissenberg, QA 0 S Engineer
  • H. P. Ehas, QA & S Ergineer

CD. C. Kramer, QA & S Engineer

  • C. A. Burgen, QA & S Engineer
  • J. B. Vorderbrueggen, Field Engineer

Henry J. Kaiser Company (HJK)

  • S. E. Heath, QA Supervisor

USNRC

  • T. Daniels, Senior Resident Inspector

Management Meeting at Site on January 18, 1980

CG&E Employees

E. A. Borgmann, Vice President

B. K. Culver, Project Manager

W. W. Schwiers, QA Manager

R. P. Ehas, QA and S Engineer

4

J. B. Vorderbrueggen, Field Engineer

D. Waymire, Manager of General Engineering Department

HJK Employees

R. Marshall, Project Manager

K. R. Baumgarten, QA Manager

USNRC

I. T. Yin, Reactor Inspector

T. E. Vandel, Project Inspector

T. Daniels, Senior Resident Inspector

R. C. Knop, Section Chief-

G. Fiore111, Branch Chief

  • Denotes those attending the exit interview of December 28, 1979.

-2-

_

_ _

_ ,

. . - - . . - .

_.

_.

_

-=.

.

=

.

Licensee Action on Previously Identified Items

.

(0 pen) Noncompliance Item (358/79-22-03):

Inadequate hanger and snubber

storage and nonconformance control. The inspector observed the storage

building and saw improvement in overall arrangements.

The storage areas

were divided in groups of excess material, void and deleted material, and

useable material, which were not defined in the licensee procedure No.

FCP2-138, " Hanger Componet Cleaning and Reconditioning in Hanger Storage",

Revision 0, dated September 27, 1979. The inspector requested clarifica-

tion of the requirement for restoratiou of material prior to placing in

the "usesble" areas and stated the need for better control of scattered

'

,

scrap materials outside the storage buildings. The licensee committed

to revise procedure No. FCP2-138, and improve the handling of the scrap

material.

(Closed) Unresolved Item (358/79-22-02):

Inadequate site document control.

The licensee performed an audit in the subject area on August 27-31, 1979,

4

and the findings were recorded in CG&E QA and S Audit / Surveillance Report

No. 263. While the audit was considered sufficient, the corrective action

was not considered to be adequate. This is part of the item of noncom-

pliance described in Paragraph 5.d. of this report.

Functional or Program Areas Inspected

1.

A-E Review on Safety Related Hangers and Restraints

>

'

The status of the subject matter submitted form S&L to the licensee

was reviewed by the inspector. Among the estimated 5,100 essential

and seismic hanger items, 2,179 have been evaluated.

Among the 2,179

items, only 774 of the original design were checked and found to be

acceptable. The trend of major or minor redesign effort was increased

form 50% as reported in July 1979, (RIII Report No. 50-358/79-22) to

64% as of this report.

'

2.

Inadequate Hanger and Snubber Inspection

To the date of this inspection, none of the variable and constraint

spring hangers, and the hydraulic or mechanical snubbers have been

final inspected and accepted by the licensee.

While the craft was

modifying and installing approximately 1,572 safety and non-safety

hanger items thru November 1979, HJK QA installation inspection

surveillance of hangers per procedure No. FCP 2-135, " Process Pipe

Support Installation After S&L Final Design Analysis", Revision 3,

dated July 19, 1979, has been stopped since receipt of a CG&E letter,

dated September 6,1979, stating, " Verification of configuration and

location of seismic hangers is not the responsibility of the

Henry J. Kaiser inspection forces."

-3-

--

-_ .

.

Even before September 6, 1979, the HJK QA was only performing spot

'QC hanger inspection on one out of 15 to 20 installations. The

.present problem also involves inadequate guidance in regard to the

acceptance criteria and documentation for the HJK engineering to

" visually verify all hanger installations for completeness and com-

pliance in accordance with the specifications, approved drawings,

DDC's, and the criteria stated within this procedure" as required

in HJK procedure No. FCP 2-135, Revision 3, paragraph 2.2.8.

The

problem was further compounded by the fact that there were approxi-

mately 1,000 Design Document Changes (DDC's) not finally approved

by S&L, and this meant no final QC acceptance on these installations.

Also with the limited work force under the CG&E Hanger Engineer they

could only afford to inspect the items required immediately prior to

system pre-op tests. The lack of sufficient QC inspection program

on safety related suspension system installation is considered an

item of noncompliance with 10 CFR 50, Appendix B, Criterion X, and

. William H. 7.immer, . Unit 1, FSAR Paragraph 17.1.10 requirements.

(358/79-37-01)

3.

Inadequate Procedure Control and Implementation

As stated in Paragraph 2 above, the HJK QA had stopped their hanger

inspection surveillance effort after receiving the CG&E letter dated

September 6, 1979. Although this action was apparently contrary to

procedure No. FCP 2-135, Revision 3, Paragh 2.2.10 (b) and (d) which

states that HJK QA inspection shall perform installation inspection

surveillance of hangers and perform construction inspection in ac-

cordance with QACMI M-12, a request for clarification of the letters

intent, or a revision to the FCF prior to work implementation Md

never been made.

In addition, Paragraph 2.2.2 of the HJK proce ure

No. FCP2-135, Revision 3, which states, "KEI Engineering will review

all preliminary (progress print) reissued drawings for feasibility of

installation. All changes will be concurred with by CG&E site hanger

department and returned to S&L, Chicago." This procedure had not been

changed to reflect the present arrangement to have an outside consultant,

Nuclear Power Services, performing the HJK and CG&E functions as stated

in the procedure.

The use of licensee correspontiance to document work instructions

and failure to update the controlled procedure is considered an

item of noncompliance with 10 CFR 50, Appendix B, Criterion VI,

and William H. Zimmer, Unit 1, FSAR Paragraph 17.1.6 requirements.

(358/79-37-02)

4.

Inadequate Protection for B-P Hydraulic Snubbers

During an inspection inside the containment, four B-P snubbers on

RH01B18-36 line were observed without accumulator indicator pro-

tective covers or with inadequate covers. Three similar conditions

i

-4-

.

.

.'

were observed outside the containment in the reactor building.

Furthermore, many B-P. snubbers were installed on walkways and were

covered with dust, dirt, and mud.

The requirement for B-P accumula-

tor covers to prevent entry of foreign matter into the cavity was

discussed in RIII Report No. 50-358/78-10, Paragraph 5.b.

A Noncon-

formance . Report, No. 7424 was issued by the licensee on December 27,

1979.

Failure to protect safety related component during installation is

considered an item of noncompliance with 10 CFR 50, Appendix B,

Criterion XIII and William H. Zimmer, Unit 1, FSAR Paragraph 17.1.13

requirements. (358/79-37-03).

5.

Inadequate Licensee Corrective Action

'

The noncompliance items identified in this report are similar to

problems identified previously by the RIII inspector. These include:

a.

The inadequate hanger inspection program as described in Par-

agraph 2 of this report was previously cited in RIII Report

No. 50-358/78-18,Section II , Paragraph la and b.

(358/78-18-01)

b.

The use of company correspondence in lieu of an approved work

procedure as described in Paragraph 3 of this report, the lack

of control of procedures, and the failure to correct the in-

spector identified problems were previously documented in RIII

Report 50-358/78-18,Section II Paragraph 2 (358/78-18-02),

and Paragraph 3 (358/78-18-03); and RIII Report 50-358/78-32,

Pa ragraph 3 (358/78-32-01).

c.

The lack of protective mrasures for the B-P hydraulic snubbers

as described in Paragraph 3 of this report was once cited in

RIII Report 50-358/78-18,Section II, Paragraph 4 (358/78-18-04).

d.

In review of CG&E QA & S Audit / Surveillance Report No. 263,

dated August 27-31,'1979, a deficiency was identified relative

to document issuance control of the CG&E construction and test

procedures. The audit finding response by the CG&E Construct

Department through and Inter-Department Correspondence, dated

September 18, 1979, stated, ".

. addressee to return a signed

.

copy of the letter as acknowledgement of the procedure." The

inspector reviewed the document file in CG&E Construction

Department and considered the corrective action inadequate, in

that (1) no approved procedure on how to handle the issuance

of work procedures including all subsequent revisison was estab-

lished-and (2) no effort was made to check all work-procedures

received by the addressee and to assure that the up-to-date

revisions were in their work location.

-5-

l

l

.

This is considered an item of noncompliance with 10 CFR 50,

.-

Appendix B, Criterion XVI, and William H. Zimmer Unit 1, FSAR

Paragraph 17.1.16 requirements. (358/79-37-04)

6.

Followup Management Discussions

Subsequent to the December 27-28, 1979, site inspection, RIII

management held discussions with the CG&E Vice President and his

Ftaff through conference telephone calls on January 2 and 9, 1980.

Besides the concern for the repeated problems as identified in

this report, there was also a question relative to CGE allowing

field engineers to perform the quality control inspection work.

The involved CG&E field engineers not only worked under the depart-

ment that had direct control over cost and scheduling of the con-

struction activity, but also, were involved in reviewing the design

documents and supervising the system installations.

Since no resolu-

tion was reached during the conference telephone conversations, a

-management meeting was planned for January 18, 1980 at the site.

7.

Followup Program Inspection

On January 17, 1980, the inspector reviewed the revised CG&E HJK

work procedures relative to the pipe suspension system site quality

control inspection measures and determined that there were no notice-

able changes or improvements in the overall program except some

clarification was made on HJK field engineer responsiblities, and

HJK QA surveillance sampling inspection requirements. The procedures

reviewed included:

CG&E Mechanical Construction Test Procedure No. MC-5, " Pipe

.

Support Final Inspection", Revision 3, dated January 16, 1980.

HJK Field Construction Procedure No. 2-135, " Process Pipe

.

Support Installation After S&L Final Design Analysis", Revision

5, dated January 14, 1980.

HJK Quality Assurance - Construction Methods Instruction No.

.

M-12, " Inspection Instruction for Pipe Hangers, Support, and

Restraint Installation", Revision 3, dated January 17, 1980.

8.

Summary of the Meeting

The management and staff of the NRC, CG&E, and HJK held a meeting

at the site on January 18, 1980, to discuss the pipe suspension

program adequacy. The proposed program presented by the licensee

included:

Pipe suspension systems will be installed by HJK construction

a.

personnel.

-6-

..

  • -

b.

HJK QA will perform inspections during installation and will

document any problems identified in nonconformance reports

(NR's). The' inspection will include (1) 100% installation

verification of welding, and anchor bolts, and (2) 10% in-

spection of hanger and restraint system installations relative

to configuration and location.

Inspection would increase if

problems were identified.

c.

HJK field engineers will review design drawings and check

conditions prior to installation. Design Document Changes

(DDC's) will be prepared if design implementation was im-

possible, or difficult. Verification will be made after

installation.

.

d.

CG & E General Construction Department (GCD) field engineers,

(called Support Group) will inspect hanger and restraint con-

figuration and location during installations.

NR's will be

prepared if problems are identified.

CG & E QA will perform audits on CG & E GCD performance.

e.

f.

HJK QA will perform audits on HJK engineering, construction,

and inspection performance.

In conclusion the NRC staff stated:

Measures provided in items a, c, e, and f were considered to

.

be acceptable.

.In regard to item b,100% QC inspection on hanger and restraint

.

configuration and location should be performed by an organiza-

tion that is independant of construction procedures including

the detail checklists.

In regard to item d,'the GCD Support Group can not perform QC

.

inspection of hanger configuration and location inspection since

GCD is assigned the responsibility for construction scheduling-

and costs. The 200 plus safety related essential supports

inspected by the GCD Support Group are considered unacceptable

based on the above reason, the fact that the HJK QA procedure

had not been used, and'that there was no documentation to show

the depth and the detail of the inspection performed.

The licensee will inform Region III of their corrective measures

.

for the items discussed'during the meeting within two weeks

including, (1) time period established for QC inspection after

hanger installation, (2) QC inspection documentation, and (3)

establishment of independance for the QC inspection personnel

away from engineering,~ supervising, cost control,'and scheduling

activities.

-7-

L

7.

...

, Exit Interview.

.

,

The inspector met with licensee representatives (denoted in the Person

Contacted paragraph) at the conclusion of the inspection on December-28,

.1979. The inspector summarized the purpose-and findings of the inspection.

' The licensee acknowledged the findings reported herein.

s

I

4

4

4

4

,

!

i -.

$

1

z

3

I .

'~.8-

<

.

_.