Text

b

4 e..

TN

UNITED STATES

p tgyq

4

o

NUCLEAR REGULATORY COMMIS510N

j

3

o

REGION I

3-

.$

s31 PARK AVENUE

"p

KING OF PRUS$3 A, PENNSYt.V ANIA 19406

JM 2 2.m

Dock 2t No. 50-423

Northeast Nuclear Energy Company

ATTN: Mr. W. G. Counsil

Vice President - Nuclear

Engineering and Operations

P. O. Box 270

Hartford, Connecticut 06101

Gentlemen:

Subject:

Inspection Report No. 50-423/79-12

This refers to the inspection conducted by Mr. A. Cerne of this office

on December 27-28, 1979 at the Millstone Nuclear Power Station, Unit 3

at Waterford, Connecticut of activities authorized by NRC License No.

CPPR-ll3 and to the discussions of our findings held by Mr. Cerne with

Mr. S. Toth and others of your staff at the conclusion of_ the inspection,

and to a subsequent telephone discussion between Mr. Cerne and Mr. Toth

on December 31, 1979 and January 3, 1980.

Areas examined during this inspection are described in the Office of

Inspection and Enforcement Inspection Report which is enclosed with this

letter. Within these areas, the inspection consisted of selective

examinations of procedures and representative records, interviews with

personnel, and observations by the inspector.

Within the scope of this inspection, no items of noncompliance were

observed.

In a::cordance with Section 2.790 of the NRC's " Rules of Practice," Part

2, Title 10, Code of Federal Regulations, a copy of this letter and the

enclosed inspection report will be placed in the NRC's Public Document

Room.

If this report contains any information that you (or your contractor) _

believe to be proprietary, it is necessary that you make a written

application within 20 days to this office to withhold such information

from public disclosure. . Any such application must be accompanied by an

affidavit executed by the owner of the information, which identifies the

document or part sought to be withheld, and which contains a statement

of reasons which addresses with specificity the items which will be

considered by the Commission as listed in subparagraph (b) (4) of Section

2.790.

The information sought to be withheld shall be incorporated as

far as possible into a separate part of the affidavit.

If we do not

hear from you in this regard within the specified period, the report

will be placed in the Public Occument Room.

8003190905

-,

..

_

s

..

Northeast Nuclear Energy Company

2

No reply'to this letter is required; however, should you have any questions

concerning this inspection, we will be pleased to discuss them with you.

Sincerely,

/obert T. Carls$"f

on, Chie

Reactor Construction and Engineering

Support Branch

. Enclosure:

Office of Inspection and Enforcement Inspection

Report Number 50-423/79-12

cc w/ encl:

K. W. Gray, Construction Quality Assurance Lead

H. R. Nims, Director of Nuclear Projects

J. F. Opeka, Station Superintendent

J. R. Himmelwright, Licensing Safeguards Engineer

I