COMPONWEALTH EDISON COWANY LASALLE COUNTY STATION, UNITS NO.1 AND NO. 2 DOCKET NOS. 50-373 AND NO. 50-374 ORDER EXTENDING CONSTRUCTION C0FPLETION DATES Commonwealth Edison Company is the holder of Construction Permits Nos. CPPR-99 and CPPR-100 issued by the Atomic Energy Conmission* on Sep-tember 10, 1973, for the construction of the LaSalle County Station, Units No.1 and No. 2, presently under construction at the applicant's site in Brookfield Township, LaSalle County, Illinois.
On September 24, 1979, the applicant requested an extension of the latest canpletion dates because construction has been delayed due to:
(1)
A labor strike and work stoppage; (2)
Insufficient craft manpower; (3 )
Modifications in the suppression pool as a result of staff criteria, and (4 )
Additional requirements by the staff in the area of fire protection and testing.
- Effective January 20, 1975, the Atomic Energy Commission became the Nuclear Regulatory Commission and permits in effect on that day were continued under the authority of the Nuclear Regulatory Commission.
O 8002130
/2/
7590-01 This action involves no significent hazards consideration; good cause has been shown for the delay; and the requested extension is for a reasonable period, the bases for which are set forth in the staff's evaluation dated January 11, 1980 The preparation of an environmental impact statement for this particular action is not warranted because there will be no environmental impact attribut-able to the actions authorized by the Order other than that which has already been predicted and described in the Commission's Final Environmental Statement-Operating License Stage for the LaSalle facility, published in November 1978, and the Final Environmental Statement-Construction Permit Stage, published in February 1973. A Negative Declaration and an Environmental Impact Appraisal have been prepared and are available, as are the above stated documents, for public inspection at the Commission's Public Document Room,1717 H Street, N.
W.,
Washington, D. C. 20555 and at the local public document room established for the LaSalle facility in the Illinois Valley Community College Library, Rural Route No.1, Oglesby, Illinois 16348.
o
7590-01 It is HEREBY ORDERED that the latest completion date for CPPR-99 be extended f rom March 31, 1980 to June 30, 1981 and for CPPR-100 from December 31, 1980 to March 31, 1982.
FOR THE NUCLEAR REGULATORY COMMISSION A
(
Y D. F. Ross, Jr., Acting Director Division of Project Management Office of Nuclear Reactor Regulation Date of Issuance: