ML19305A393
| ML19305A393 | |
| Person / Time | |
|---|---|
| Site: | Crane |
| Issue date: | 04/11/1979 |
| From: | Grier B NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I) |
| To: | Herbein J METROPOLITAN EDISON CO. |
| References | |
| NUDOCS 7905020053 | |
| Download: ML19305A393 (1) | |
Text
i
\\
- hdh580 UNITED STATES 0g gt
.,g NUCLEAR REGULATORY COMMISSION REGION 1 y
o U
f 631 PARK AVENUE C,
f x NG OF PRUS$1 A. PENNSYt.VANI A 19406 April 11, 1979 Docket No. 50-289 Metropolitan Edison Company ATTN: Mr. J. G. Herbein Vice President - Generation P. O. Box 542 Reading, Pennsylvania 19640 Gentlemen:
The enclosed Bulletin 79-06 is forwarded to you for information.
No written response is required.
If you desire additional information regarding this matter, please contact this office.
Sincerely,
[
Boyce H. Grier
~ ~ Director
Enclosure:
IE Bulletin No. 79-06 with Enclosures cc w/encls:
E. G. Wallace, Licensing Manager J. J. Barton, Project Manager L. L. Lawyer, Manager - Generation Operations G. P. Miller, Manager - Generating Station - Nuclear J. L. Seelinger, Unit 1 Superintendent W. E. Potts, Unit 1 Superintendent - Technical Support I. R. Finfrock, Jr.
Mr. R. Conrad G. F. Trowbridge, Esquire Miss Mary V. Southard, Chairman, Citizens for a Sefe Environment 3905020 ga
r, UNITED STATES NUCLEAR REGULATORY C0ffilSSION OFFICE OF INSPECTION AND ENFORCEMENT WASHINGTON, D.C.
20555 Apr.il 11,1979 IE Bulletin No. 79-06 Page 1 of 4 REVIEW 0F OPERATIONAL ERRORS AND SYSTEM MISALIGNMENTS IDENTIFIED DURING THE THREE MILE ISLAND INCIDENT As previously discussed in IE Bulletin 79-05 and 79-05A, the Three Mile Island Nuclear Power Plant, Unit 2 experienced significant core damage which resulted from a series of events initiated by a loss of feedwater transient and apparently compounded by operational errors.
Several aspects of the incident have generic applicability to all light water power reactor facilities, in addition to those previously identified as applicable to Babcock and Wilcox reactors.
This bulletin is to identify certain actions to be taken by all other light water power reactor facilities with an operating license. Actions previously have been required of licensees with B&W reactors.
Action to be taken by licensees:
For all pressurized water power reactor facilities with an operating license except Babcock and Wilcox reactors:
1.
Review the description of circumstances described in Enclosure 1 of IE Bulletin 79-05 and the preliminary chronology of the TMI-2 3/28/79 accident included in Enclosure 1 to IE Bulletin 79-05A.
a.
This review should be directed toward understanding: (1) the extreme seriousness and consequences of the simultaneous blocking of both auxiliary feedwater trains at the Three Mile Island Unit 2 plant and other actions taken during the early phases of the accident; (2) the apparent operational errors which led to the eventual core damage; and (3) the necessity to systematically analyze plant conditions and parameters and take appropriate corrective action.
b.
Operations personnel should be instructed to:
(1)notoverride automatic action of engineered safety features without careful review of plant conditions; and (2) not make operational decisions based on a single plant parameter indication when a confirmatory indication is available.
c.
All licensed operators and plant management and supervision with operational responsibilities shall participate in this review and such participation shall be documented in plant records.