UNITED STATES
[cf z
- g NUCLEAR REGULATORY COMMISSION 3
g REGION I f
$31 PARK AVENUE
[
KING OF PRUSSIA. PENNSYLVANIA 19406 3
Docket No. 50-423 Northeast Utilities Service Co.
ATTN: Mr. W. G. Counsil Vice President Nuclear Engineering & Operations P. O. Box 270 Hartford, Connecticut 06101 Gentlemen:
Subject:
Vendor QA Program Breakdown - Tubeco (Your letter of January 29,1979)
Thank you for your letter, referenced above, which forwarded a final report pursuant to 10 CFR 50.55(e) regarding the subject matter.
This matter will be reviewed during our next inspection.
Your cooperation with us is appreciated.
Sincerely,
[
e --
Robert T. Carlson, Chief Reactor Construction and Engineering Support Branch cc:
K. W. Gray, Construction Quality Assurance Lead H. R. Nfms, Director of Nuclear Projects J. F. Opeka, Station Superintendent J. R. Himmelwright, Licensing Safeguards Engineer 7903080678
NOFITHEAST NORTHEAST UTILITIES SERVICE COMPANY r,?hl?OunEC,1 cur osto' L!TifalTISS January 29, 1979 United States Nuclear Regulatory Commission ATTN:
Mr. B. H. Grier, Director Office of Inspection and Enforcement Region I 631 Park Avenue King of Prussia, Pennsylvania 19406 Gentlemen:
Docket No. 50-423 AEC-MP3-178
SUBJECT:
Millstone Unit No. 3 WGC-79-3-21 Reporting of Deficiencies In Desion & Construction
References:
1.
D.C. Switzer letter to Dr. D.C. Knuth, dated February 18,1976 ( AEC-MP3-109).
2.
D.C. Switzer letter to J.P. O'Reilly, dated September 8,1976 (AEC-MP3-ll7).
3.
D.C. Switzer letter to J.P. O'Reilly, dated April 19,1977 ( AEC-MP3-140).
4.
D.C. Switzer letter to B.H. Grier, dated November 15,1977 (AEC-MP3-158).
5.
D.C. Switzer letter to B.H. Grier, dated March 9,1978 (AEC-MP3-167).
6.
W.G. Counsil letter to B.H. Grier, dated June 15,1978 ( AEC-MP3-171).
Please refer to our letter dated June 15,1978, AEC-MP3-171, in which we stated that we had inspected 50 Category I pipe spools of TUBEC0 and would report again when our inspection effort on 100 spools was complete.
The inspection of 100 QA Category I pipe spools of TUBEC0 has now been completed.
The results of this inspection indicate that TUBECO has properly-implemented its QA Category I program.
During this period, however, TUBECO itself, identified to our agent an occurrence of improper material usage.
As a result of this, and in order to provide additional assurance of code compliance, the inspection hold point on the pipe cutting operation is being retained on ASME III work.
In addition, documentation for ASME III piping and spools is being reviewed prior to releasing hardware for shipment in accordance with our agent's standard pro ram, N hckh et cou.tcTeet oo-T mo rev.ta coupua
-t >,gaTrc=y t' tcTP c uoHT ccupen
We believe these measures, in conjunction with continued periodic audits of TUBEC0's QA program, provide adequate assurance of TUBECO's quality performance; and we consider the above-referenced-Deficiency Report satisfactorily resolved.
Very truly yours, NORTHEAST NUCLEAR ENERGY COMPANY
/
U)1dv'(
W. G. Counsil Vice President Nuclear Engineering & Operations cc:
United States Nuclear Regulatory Commission Office of Inspection and Enforcement Washington, D.C.
20555