Caseload Forecast Panel Update of Facility Fuel Load Date of March 1979 Is Believed Optimistic.Requests Certain Info by Early Jan 1979 in Order to Review Const Completion Status & Update Panels Projected Fuel Load Date
ML19305A168
Person / Time
Site: LaSalle  
Issue date: 12/20/1978
From: Parr O
Office of Nuclear Reactor Regulation
To: Delgeorge L
COMMONWEALTH EDISON CO.
References
NUDOCS 7901040315
Download: ML19305A168 (3)


Text

-

f UselTED STATES 1

NUCLEAR REGULATORY COMMISSION g

{

g..Q:)p

,{,

WASHINGTON. D. C. 20555 o, 'n.JIfk

/

/

DEC 2 0 ble Docket Nos.

50-373 and 50-374 Mr. L. O. DelGeorge Nuclear Licensing Administrator Boiling Water Reactors Commonwealth Edison Company P. O. Box 767 Chicago, Illinois 60690

Dear Mr. DelGeorge:

SUBJECT:

CASELOAD FORECAST PANEL UPDATE OF THE LA SALLE STATION UNIT 1 FUEL LOAD DATE As you are aware the Caseload Forecast Panel visited the La Salle site on August 1,1978. Based on that visit and discussions with your staff the panel concluded that your projected fuel date for Unit 1 of March 1979 was optimis-tic.

We stated at that ~.ime that we would be reviewing your construction completion status after the first of the year to update the panel's projected fuel load date.

In order that we may perform this update, please provide the information contained in the Enclosure by early January 1979.

Please contact us if you desire any discussion or clarification of these matters.

Since,ely,

&{ $.

Ulan D.

>arr, Chief Light Water Reactors Branch No. 3 Division of Project Management

Enclosure:

As stated cc w/ enclosure:

See next page 7901040316

Mr. Byron Lee, J r.

Vice President Commonwealth Edison Company P. O. Box 767 Chicago, Illinois 60690 cc: Richard E. Powell, Esq.

Isham, Lincoln & Beale One First National Plaza 2400 Chicago, Illinois 60670 Dean Hansell, Esq.

Assistant Attorney General State of Illinois 188 West Randolph Street Suite 2315 Chicago, Illinois 60601

J ENCLOSURE LA SALLE 1 & COMMON - STATUS AS OF DECEMBER' 3.1, 1970 1.

Was General Electric stress report released in October?

2.

Status of hanger design?

3.

Bulk quantity Unit 1 & Common:

(a) Large bore pipe - remaining to be installed, (b) Small bore pipe - remaining to be installed, (c) Hangers snubbers - remaining to be installed, (d)' Number of hangers / snubbers yet to be fabricated and delivered to the site, (e) Cable - linear feet remaining to be installed, (f) Cable tray - linear feet remaining to be installed, (g) Conduit - linear feet remaining to be installed, and (h) Terminations - number remaining, 4

Pre-Op Tests and Procedures:

(a) Number draft procedures not completed, (b) Number draft procedures issued for comment, (c) Number in final preparation, (d) Procedures at engineering for approval, (e) Number of procedures approved, (f) Number of pre-op tests completed, and (g) Number of pre-op tests ongoing.

5.

Overall percent complete as of December 31, 1978.

6.

Is turbine snield wall concrete complete?

7.

Linear feet cable pulled per month since August 1,1978.

8.

Will replacement of thermal sleeves and safe ends impact schedule?

9.

Any additional impact on schedule with respect to Mark II containment.