Supplements 791005 Response to IE Insp Repts 50-324/79-19 & 50-325/79-19.Completion of Review of Util Corporate QA Program, Parts 2 & 3, Delatyed Due to Manpower Requirements Resulting from TMI Incident
ML19296D794
Person / Time
Site: Brunswick  Duke Energy icon.png
Issue date: 02/19/1980
From: Tollison A
CAROLINA POWER & LIGHT CO.
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
BSEP-80-287, NUDOCS 8003130220
Download: ML19296D794 (1)


Text

- -,

. 2C CD&L Carolina Power & Light Company Brunswick Steam Electric Plant Q

{

P. O. Box 458

~

m

[3)

O Southport, NC 28461 d

m February 19, 1980 g

FILE: B3514 SERIAL: BSEP/ -287 t.c Mr. Jamcs P. O'Reilly, Director U. S. Nuclear Regulatory Cortmission Region II 101 Marietta Stre-6 Suite 3100 Atlanta, GA 30303 BRUNSWICK STEAM ELECTRIC PLANT, UNIT NOS. 1 & 2 LICENSE NOS. DPR-71 AND DPR-62 DOCKET NOS. 50-325 AND 50-324 SUPPLEMENT TO RESPONSE TO IE INSPECTION REPORT 324-325/79-19

Dear Mr. O'Reilly:

In our response to IE Inspection Report 324-325/79-19, dated October 5, 1979, Serial Number GD-79-2472, we committed to a review of the CP6L Corporate Qual-ity Assurance Program, Parts 2 and 3.

This review commitment was stated in the response to Infraction C of the IE Report. A completion date of March 1, 1980 was provided.

Due to the manpower requirements relative to the programs being required as a result of Three Mile Island, it will not be possible to complete this review by March 1, 1980. Unless we are otherwise notified, this review will now be completed by June 1, 1980.

Very truly yours, A. C. Tollison, Jr., General Manager Brunswick Steam Electric Plant

</