7ZO
-
,
UNITED STATES
pa Mooq'o,
NUCLEAR REGULATORY COMMISSION
4
'
O '( .N *
'
REGloN IV
E I
c
611 RY AN PLAZA DRIVE, SUITE 1000
j
ARLINGTON, TEXAS 76012
5*'>
J
c.
-
% .... /
January 29, 1980
In Reply Refer To:
RIV
Docket No.
50-458/Rpt. 80-01
Gulf States Utilities
ATTN:
Dr. J. G. Wcigand, Vice President
River Bend Operations and Technical
Systems
Post Office Box 2951
Beaumont, Texas
77704
Gentlemen:
This refers to the inspection ec.
ted by Sc. C. R. Oberg and other members
of our staff during the periods Juuary 9-11 and 14-18,1980, of activities
authorized by NRC Construction Permit No. CPPR-145 for River Bend, Unit No.
1, and to the discussion of our findings with Mr. T. L. Crouse and other
members of your staff at the conclusion of the inspection.
Areas examined during the inspection and our findings are discussed in the
enclosed inspection report. Within these areas, the inspection consisted of
selective examination of procedures and representative records, interviews
with personnel, and observations by the inspectors.
Within the scope of the inspection, no items of noncompliance were identified.
We have also examined actions you have taken with regard to previously identi-
fied inspection findings.
The status of these items is identified in paragraph
2 of the enclosed report.
In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2,
Title 10, Code of Federal Regulations, a copy of this letter and the enclosed
inspection report will be placed in the NRC's Public Document Room.
If the
report contains any information that you believe to be proprietary, it is
necessary that you submit a written application to this office, within 20 days
of the date of this letter, requesting that such information be withheld from
public disclosure.
The application must include a full statement of the reasons
why it is claimed that the information is proprietary.
The application should
be prepared so that any proprietary information identified is contained in an
enclosure to the application, since the application without the enclosure will
also be placed in the Public Document Room.
If we do not hear from you in this
regard within the specified period, the report will be placed in the Public
Document Room.
8003120 7 2 3
.
Gulf States Utilities
2
January 29, 1980
Should you have any questions concer-dng this inspection, we will be pleased
to discuss them with you.
Sincerely,
'
,
W.C.Seihe, Chief
Reactor Construction and
Engineering Support Branch
Enclosure:
IE Inspection Report No. 50-458/80-01
.
/
9