ML19296D234
| ML19296D234 | |
| Person / Time | |
|---|---|
| Site: | Comanche Peak |
| Issue date: | 01/08/1980 |
| From: | Seidle W NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV) |
| To: | Gary R TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC) |
| Shared Package | |
| ML19296D235 | List: |
| References | |
| NUDOCS 8003030051 | |
| Download: ML19296D234 (2) | |
See also: IR 05000445/1979027
Text
/7C
~
UNITED STATES
[pa*E%,%,
NUCLEAR REGULATORY COMMISSION
'
f&
. /'
REGloN IV
'
2 '. i ' ': $
611 RY AN PLAZA DRIVE, SUITE 1000
j
ARLINGTON, TEX AS 76012
7
o,4
$gy , c
%....)./
1
>~
January 8, 1980
In Reply Refer To:
RIV
Docket No. 50-445/Rpt. 79-27
50-446/Rpt. 79-26
Texas Utilities Generating Company
ATTN:
Mr. R. J. Gary, Executive Vice
President and General Manager
2001 Bryan Tower-
Dallas, Texas
75201
Gentlemen:
This refers to the inspection activities performed by our Resident Inspector,
Mr. R. G. Taylor, for the period of November 1979, of activities authorized
by NRC Construction Permits No. CPPR-126 and 127 for the Comanche Peak
facility, Units No. I and 2, and to the discussion of our findings with
Mr. R. G. Tolson and other members of your staff during the inspection
period.
Areas examined during the inspection and our findings are discussed in the
enclosed inspeccion report. Within these areas, the inspection consisted of
selective examination of procedures and representative records, interviews
with personnel, and observations by the inspector.
During the inspection, it was found that certain activities under your
license appear to be in noncompliance with Appendix B to 10 CFR 50 of the
NRC Regulations, " Quality Assurance Criteria for Nuclear Power Plants."
The Notices of Violation for the items of noncompliance reported in the
enclosed inspection report were forwarded to you by our letters dated
November 15 and 21, 1979; therefore, this letter does not require further
response regarding this matter.
We have also examined actions you have taken with regard to previously
identified inspection findings.
The status of these items is identified
in paragraph 2 of the enclosed report.
gg3030 b
,
Texas Utilities Generating Company
2
January 8, 1980
One new unresolved item is identified in paragraph 7 of the enclosed
report.
In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2,
Title 10, Code of Federal Regulations, a copy of this letter and the enclosed
inspection report will be placed in the NRC's Public Document Room.
If the
report contains any information that you believe to be proprietary, it is
necessary that you submit a written application to this office, within 20
days of the date of this letter, requesting that such information be withheld
fro.2 public disclosure. The application must include a full statement of the
res;ons why it is claimed that the information is proprietary.
The application
should be prepared so that any proprietary information identified is centained
in an enclosure to the application, since the application without the enclosure
will also be placed in the Public Document Room.
If we do not hear from you in
this regard within the specified period, the report will be placed in the Public
Document Room.
Should you have any questions concerning this inspection, we will be pleased
to discuss them with you.
Sincerely,
h
h-
W. C. Sei le, Chief
Reactor C 'struction and
Engineering Support Branch
Enclosure:
IE Inspection Report No.50-445/79-27
50-446/79-26
cc: w/ enclosure
Texas Utilities Generating Company
ATTN:
Mr. H. C. Schmidt, Project Manager
2001 Bryan Tower
Dallas, Texas
75201