f .,%'o
,
g
UNITED STATES
g
NUCLEAR REGULATORY COMMISSION
y
)3
g
.
5
- c
FIEGION 111
799 ROOSEVELT ROAD
0,g
[
GLEN ELLYN,ILUNOIS 60137
,
+....
JM 161983
'Jocket No. 50-329
Docket No. 50-330
Consumers Power Company
ATTN:
Mr. Stephen H. Howell
Vice President
1945 West Parnall Road
Jackson, MI
49201
Gentlemen:
This refers to the inspection conducted by Mr. K. R. Naidu of this office
on December 18-20, 1979, of activities at the Midland Nuclear Power Plant,
Units 1 and 2 authorized by Construction Permit No. CPPR-81 and No. CPPR-82
and to the discussion of our findings with Messrs. D. Miller, J. Corley,
and others of your staff at the conclusion of the inspection.
The enclosed copy of our inspection report identifies areas examined during
the inspection. Within these areas, the inspection consisted of a selective
examination of procedures and representative records, observations, and
interviews with personnel.
No items of noncompliance with NRC requirements were identified during the
course of this inspection.
In accordance with Section 2.790 of the NRC's ' Rules of Practice," Part 2,
Title 10, Code of Federal Regulations, a copy of this letter and the enclosed
inspection report will be placed in the NRC's Public Document Room, except
as follows.
If this report contains information that you or your contractors
'uelieve to be proprietary, you must apply in writing to this office, within
twenty days of your receipt of this letter, to withhold such information
from public disclosure. The application must include a full statement of
the reasons for which the information is considered proprietary, and should
be prepared so that proprietary information identified in the application
is containem in an enclosure to the application.
Q
8002250
32.5
.. - . .
-... . - ...
- - ...
.
.
T
Consumers Power Company
-2-
We will gladly discuss any questions you have concerning this
inspection.
Sincerely,
f
M
,Gaston Fiore i, Chief
Reactor Construction and
Engineering Support Branch
Enclosure:
IE Inspection
Reports No. 50-329/79-29
and No. 50-330/79-29
cc w/ enc 1:
Central Files
Reproduction Unit NRC 20b
Local PDR
Ronald Callen, Michigan Public
Service Commission
Dr. Wayne E. North
Myron M. Cherry, Chicago
. . . . . .-