Responds to 791220 Request for Expeditious Decision Re Facility Restart.Aslb 791229 Order Rescinded ASLB 791130 Order Prohibiting Plant Operation.Corrective Actions to Control Bldg & Concrete Block Wall Were Adequate
ML19296B409
Person / Time
Site: Trojan File:Portland General Electric icon.png
Issue date: 01/11/1980
From: Gossick L
NRC OFFICE OF THE EXECUTIVE DIRECTOR FOR OPERATIONS (EDO)
To: Ullman A
HOUSE OF REP.
Shared Package
ML19296B411 List:
References
NUDOCS 8002200528
Download: ML19296B409 (2)


Text

.

[.m arc o

'o UNITED STATES E g 'I,,g NUCLEAR REGULATORY COMMISSION g

WASHINGTON. D. C. 20555 N

n o-

'4 g '.v

,#a

  • ..+

Docket No. 50-344 JAN 11 E The Honorable Al Ullman United States House of Representatives Washington, DC 20515

Dear Congressman Ullman:

This responds to your letter of December 20, 1979, addressed to Chairman Ahearne, in which you express the need for an expeditious decision on whether the Trojan Nuclear Plant in Oregon, shut down because of certain seismic design problems, should be permitted to resume power operation. Because the question of the adequacy of proposed modifications to correct specific seismic design deficiencies at the Trojan facility is pending before an NRC Atomic Safety ar.d Licensing Board and its rulings and decisions may be subject to review by the Commissioners, including Chairman Ahearne, it was considered inappropriate for h!m to respond to your letter. Accordingly, your letter was referred to me for response.

In your letter you indicate that, because of the uncertain energy situation in the Pacific Northwest, a decision on whether or not Trojan will be permitted to operate is needed as soon as possible for energy planning purposes.

In this regard, a hearing was held in Portland, Oregon on December 28 and 29, 1979 by an NRC Atomic Safety and Licensing Board which considered the question as to whether Trojan should be permitted to operate. Based on the record made at that hearing, the Licensing Board rescinded a prior order of November 30, 1979 pro-hibiting plant operation in an order from the bench issued on December 29, 1979.

A brief description of the background of seismic design problems at Trojan will serve to describe the NRC actions which have been, and are being, taken to resolve the identified seisuic problems and assure plant safety. In April, 1978, certain deficiencies in the seismic design of the Control Building at the Trojan facility were discovered and reported to the NRC by the licensee, Portland General Electric Company.

Extensive.nalyses and evaluations of the earthquake-resisting capability of the structure were performed by the licensee and the NRC Staff and, after hearings held in October, November and December of 1978, an Atomic Safety and Licensing Board determined that the facility was safe to operate for an interim period until modifications could be implemented to correct the design deficiencies. On December 22, 1978, the NRC authorized resumption of operation of the facility pending approval of the proposed modi-fications after additional hearings before the Licensing Board. Those hearinge are scheduled to commence on April 1, 1980.

so02200 Fa r

The Honorable Al Ullman On October 12, 1979, the Trojan facility was shut down because of steam generator tube leakage.

Shortly after that shutdown, an additional problem was discovered with regard to the ability of concrete block walls to with-stand earthquake-induced forces from piping attached to those walls.

On October 22, 1979 and December 20, 1979, the NRC's Office of Inspection and Enforcement issued immediate action letters to the Trojan licensee documenting the licensee's agreement to remain shut down until the concrete block wall problem was resolved to the satisfaction of the NRC Staff.

Although the concrete block wall problem discovered in October, 1979 was independent of the Control Building design deficiencies, the Licensing Board in the Control Building proceeding expressed a concern over the safety of interim operation and over the fact that the proposed modifications to correct the Control Building design deficiencies had not yet been adjudicated.

Accordingly, on November 30, 1979, the Licensing Board ordered that the facility remain in the shutdown condition pending further Board order. As previously mentioned, a hearing at which the Licensing Board's c;ncerns were addressed was held on December 28 and 29, 1979, and, based on the 'ecord made at that hearing, the Licensing Board rescinded its November 30, 1979 order prohibiting resumption of operation in an order issued on December 29, 1979.

Following the hearing on December 29, protracted meetings between NRC Staff structural analysts, an engineer from the Oregon Department of Energy and the licensee's technical personnel and consultants were held on December 29, 30 and 31, 1979.

Based on the NRC Staff's detailed evaluation of information and analyses on the concrete block wall problem presented previously and at these meetings, the Staff determined that the corrective actions implemented by the licensee were adequate from a safety standpoint, that the concrete block wall problems were satisfactorily resolved, and that there was no basis for requiring the plant to remain shutdown. Accordingly, by letter dated December 31, 1979, the NRC's Office of Inspection and Enforcement removed the restrictions on plant operation as of that date.

The Trojan facility returned to power operation shortly thereafter.

Although, of necessity, the sole concern of both the Liernaing Board and the NRC Staff with regard to the resumption of operation at Trojan was with the safety of operation, both the Board and the Staff were cognizant of the need to reach decisions on operation as expeditiously as possible consistent with sound decisions. These decisions have now been made.

Thank you for the interest and concerns expressed in your letter of December 20, 1979.

I trust that this has been responsive to those concerns.

Sincerely, ORIGIN AL SICE.D !5Y R. C. L,.. ii Lee V. Gossick Executive Director for Operations