ML19296A240

From kanterella
Jump to navigation Jump to search
Forwards Amend 14 to Psar,Vols 1-7
ML19296A240
Person / Time
Site: 05000452, 05000453
Issue date: 03/01/1979
From:
LEBOEUF, LAMB, LEIBY & MACRAE
To: Harold Denton
Office of Nuclear Reactor Regulation
Shared Package
ML19296A242 List:
References
NUDOCS 7903020332
Download: ML19296A240 (1)


Text

>

LEBOEUF, LAM B, LElBY & M Ac R AE I757 N STREET, N.W.

WA S HIN GTO N, D, C, 2 0 0 36 T E LE

  • MON E 202 457 7500 CAeLE ADDRE SS LEON A. AL L E N, J R.

CAMERON F. Mac R A E e R AN D AL L J. LEB C E U F, J R t 92 9 - 19 75 JOSEPH E B AC H E L DE R, III CAMERON F. MAC R A E,III 4 LE SWIN, WASHINGTON, D C.

HOR AC E R. LAM B 1934 1977 E RNE ST S. D ALL AR D, JR GE R ARD A. M AHE R TEM M M O274 G. S. PE T E R BERGEN 4 SHEILA H. MARSHALL ApMN C' MIM 19 5 2 19 M GEOFFRY O C.BEST JAM E S 0. Mc C LROY T E L E coplE R DAVID P RIC M S JAMES P. Mc GR AN E R Y, JR

  • 8 YA T L OR R B RIO G S PHIL IF PA L M E R Mr GUlGAN 202-457-7643 14 0 BR OADWAY CHAHLES N. GURGE R E. EL L S WO RT H Mc M E E N,lE NE W YORK, N Y. lO O O S THOMAS E. BUR n E wiL LgAM D. MOR RISON
  • JOHN U. CHASE HARVEY A N A PI E R L

O N E 2 l2 - 2 6 9 - 14 00 ROGER D FELDMAN*4 g Ay g g g*M A L L E Y, J R. 4 CABLE ADDRESS EUGENE R. F ID E L L *

  • J. MICH AE L PARISH JACOR F RIC DL ANDE R L

B*lN,N W ORM WIL LI AM W. RO SEN BL ATT GE R ARD GIORD A NO JOHN A. RUOY TELEX 4234t6 PA T R I C M J. SCOG N AMIG LIO AME S A G EER 48 ROLD M. S EIDEL JOHN L GROSE a 4IEEN*ELEY 50UA E DOUGLAS W.HAWES S

UE

.SUGDEN LONDON Wiz SDB ENGL AND ga t g g no JAMES F. J O H N S O N, 4

EUGENE S. T HOM A S J R

  • a TELEPHONE Ot-49t 4098 RONAL O D. JONE S LEONARD M. TROST C H
  • a March 1, 1979

"'E*

'5'55 uM E S A. L-E N ~

H Aaav H. vOiGT.

LEA R.LAR50N'6 H. R6CH AR D WACH TE L GRANT i L E WI S GE R AR D P. WAT SON MIMBA W. LOVEJoy T HO M A S A. 21 E R n

  • R E SIDE N T PARTNERS W A SHI N GTON OF FIC E
  • R E SIDE NT PAR T N E R S LONDON OF FICE 4 ADMtT T E D TO THE OtSTRICT OF COLUMBI A BAR Director Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, D.C.

20555 Re:

Greenwood Energy Center Units 2 and 3; NRC Docket Nos. 50-452, 50-453

Dear Mr. Denton:

As counsel for The Detroit Edison Co-nany in the above-captioned proceeding, we submit her' three (3) originals and fifteen (15) copies of a documeat entitled

" Amendment No. 14 to Application for Licenses".

This amendment to the Greenwood 2 and 3 application is filed for the purpose of transmitting Amendment No. 14 to the Preliminary Safety Analysis Report ("PSAR").

Twenty-four (24) copies of PSAR Amendment No. 14 are also submitted herewith.

Sincerely yours, f

h 7903020332.

4 9 e.

e 4f

')

8

/

9 BEFORE THE UNITED STATES NUCLEAR REGULATORY C)MMICSION In the Matter of

)

)

THE DETROIT EDISON COMPANY

)

Docket Nos. 50-452 (Greenwood Energy Center

)

50-453 Units 2 and 3)

)

AMENDMENT NO. 14 TO APPLICATION FOR LICENSES The Detroit Edison Company, Applicant in the above captioned proceeding, hereby files Amendment No. 14 to its App 2Lcation for Licenses for the purpose of submitting Amend-ment No. 14 to the Preliminary Safety Analysis Report.

On June 4, 1973, Applicant filed with the Atomic Energy Commission its Application for Licenses to construct and operate two pressurized water reactors to be located in Greenwood Town-ship, St. Clair County, Michigan.

That App.'.ication contained, as required, a Preliminary Safety Analysis Report (PSAR).

Amendment No. 14 consists of revisions and additions to that PSAR to reflect changes in the design of the units since 1975.

In order to expedite review of the PSAR by the Commission Staff, Amendment No. 14 contains both the revised PSAR sections and those sactions that remain unchanged.

Therefore, Applicant is submitting a complete PSAR, and reference to previous PSAR material is not required.

In general, the changes in design of Greenwood Units 2 and 3 include:

79030203:39

1.

Two, single, unitized plants instead of two plants sharing major facilities such as the control building and radwaste building; 2.

A design basis safe shutdown earthquake of 0.20 g instead of 0.12 g; 3.

A 3,800 Mwt core power level instead of 3,600 Mwt; 4.

Addressing NRC Regulatory Guides 1.1 through 1.142 for the balance of plant, and Regulatory Guide 1.96 for the NSS; 5.

Incorporation of Babcock & Wilcox B-SAR-205 by reference; 6.

Utilization of the NRC Regulatory Guide 1.70, Revision 2, format in the PSAR; and 7.

Use of natural draft cooling towers instead of spray canals.

The design of the Greenwood Units is based upon the Babcock & Wilcox standardized plant referred to in B-SAR-205.

However, there are some areas in which the Greenwood nuclear steam supply (NSS) differs from B-SAR-205.

These areas are designated ae exceptions to B-SAR-205, i.e.

significant changes to the NSS as specified by B-SAR-205 or its defined interfaces that would either affect a prior B-SAR-205 safety analysis or require an NRC Staff review of an area previously approved.

A "significant change" is defined as one which would affect the ability of the NSS to perform its essential safety functions to insure:

a.

the integrity of the reactor coolant pressure boundary; b.

the fuel design limits are not exceeded; c.

the capability to achieve and maintain safe shutdown; and 2

d.

the prevention or mitigation of accident conse-quences resulting in excessive radiation expo-sure.

The exceptions from the B-SAR-205 are the following:

1.

The use of Gentile flowmoters to measure reactor coolant system flow; 2.

The Seismic Category I source of auxiliary feedwater is the nuclear service water system, not the condensate storage tank; 3.

New fuel will be stored in 13-inch center-to-center racks instead of the 21-inch racks in B-SAR-205; 4.

The chemical addition system and boron recovery sub-system are not presently within the scope of the NSS; 5.

There are differences in the fuel handling equipment, namely, the span of the fuel building bridge is greater than that speci-fied in B-SAR-205, and the fuel tube length is longer; 6.

The feedwater control valve also functions as a feedwater isolation valve; and 7.

Tube material for the decay heat coolers is inconel or equivalent.

The Greenwood reactors were purchased from Babcock &

Wilcox in 1972.

Due to the suspension of the Greenwood project, the revised PSAR addresses revisions in ASME codes.

The ASME Winter 1977 Addenda are established for components in the plant except the reactor vessel, the steam generators, and the pressurizer for which the Summer 1976 Addenda are used.

Different codes are used because many of the forgings for these components were ordered in 1973, delivered in 1974, and have been in storage since then.

While it is possible to re-examine and recertify materials, it is not possible to 3

retroactively certify an approved Quality Assurance program for the material manufacturer or qualify NDE personnel by written examination.

WHEREFORE, Applicant prays as in its Application for Licen.9es.

THE DETROIT EDISON COMPANY h,b.

By C.

M.

Heidel Executive Vice President -

Operations Subscribed apd sworn to)pefore me t is d'/

day of _ p h m -

, 1979.

bWu lu t u us ~~

.Sherrin von Allmen

/ Notary Public, Wayne County, MI My Commission expires:

Feb. 11, 1981