ML19294C170

From kanterella
Jump to navigation Jump to search
Reactor Licensing Schedule Performance Evaluation,CY76-78
ML19294C170
Person / Time
Issue date: 12/31/1978
From:
NRC COMMISSION (OCM)
To:
Shared Package
ML19294C168 List:
References
NUDOCS 8003070273
Download: ML19294C170 (25)


Text

{{#Wiki_filter:,.,.,,....... -,. 4 e REACTOR LICENSING ~ o c> SCHEDULE PERFORMANCE EVALUATION CALENDAR YEARS 1976, 197/, 1978

o DECEMBER 31,1978 9!
f,

e } a. Evaluation of Reactor Licensing Schedule Performance in 1976,1977 and 1978 Assunptions, Definitions and Comments (1) Duration data current as of 12/31/78 (2) Only first units of multi-unit OL applications are included in duration statistics (3) OL review durations have no significance. OL applications often are submitted too early. Also an OL cannot be issued until construction is complete. The only significant criterion is whether the OL was issued when the applicant and the facility were ready for fuel loading. Time to Fuel Load Ready is time i between docketing and plant ready for fuel ioading. (4) All durations are rounded to the nearest whole month (5) Target schedule is schedule duration established at review inception (6) Duration identified as " Federal Licensing Related" is obtained by subtracting from the total duration those schedule delays, designated as "Other", which are not related to the Federal licensing process. Such adjustments include State and local pennit delays, applicant construction delays and deferrals, and applicant-initiated design changes. The resulting " Federal Licensing Related" duration is that which is attributable to the requirements of the Federal agencies, including the NRC. l (7) Duration identified as "NRC Controlled" is obtained by sub-tracting from " Federal Licensing Related" duration those i schedule delays which are related to the Federal licensing i process but are beyond NRC control. Such adjustments include court decisions, late applicant submittals and discovery of natural phenomena. "NRC Controlled" is the licensing duration which is the result of the Federal licensing process and also is under NRC control. It is the schedule performance parameter by which NRC may be judged. LWA is Limited Work Authorization. CP is Construction Pennit. OL is Operating License. PDA is Preliminary Design Approval for a standardized plant design. ~~.

e .~ ' Schedule Sumary For Reactor Licensing Actions Completed in Calendar fear 1976 Average Durations in Months () W' Tire to Federal I I NRC heIensing Controlled, No. Target Total ruel Load l ated Action Issued Schedule Duration Ready Il 16 LWA's issued 2(1) 13 21 i i 26 22 CP's issued 4(9) 20 26 OL's issued 1 31 51 51 36 32 I 19 ly PDA's issued 4 13 19 i i i }i l t e e e

I I. Schedule Sumnary For Reactor Licensing Actions Conoleted in Calendar Year 1971 Average thsrations in Months _ Federal Time to Total fuel Load Licensing NRC Controlled _ O No. Target Related _ f Action issued ,diedule_ Duration Ready i 22 19 25 LWA's issued 4(F) 13 34 26 CP's issued 8(15) 19 40 a e 21 24 OL's Issued 4 22 50 49 20 16 PDA's issued 4 13 20 U e I f e O ~ l e a

4- ,*~ ~ 1 Schedule Sunnary For Reactor _ Licensing Actions Com leted in Calendar Year 1978_ n hs A_verage livrations in i l Federal NRC Time to Licensing Controlled ' Fuel Lead Related _ Total Ready b-Target Duration _ No. Schedule

  • l Action _

17 lssued 16 23 14 LilA's issued 2(4) 23 34 43 19 CP's issued 6(13) 2T 29 43 43 25 3 l OL's issued 23 25 25 15 PDA's issued 2 l O1 1 J

e f AVERAGE LWA DURATIONS (Months) e Other l H Iat i Total Duration L",,,si,, i __1 9 ~ 25 23 22 21 m 19 Target ] M Target Target ,sss ss 13 13 14 ~CY 1976 CY 1977 CY 1978 i ~

z t = AVERAGE CP DURATIONS 1 (Months)

O Other It Total Duration

=,om 43 40 s 34 34-e i 26 k N 4 26 26 g \\ e 22 Target Target 23 i Target ANNN' 20 19 19 l I e. CY 1976 CY 1977 CY 1978 I

.,.o* ~ ' ,...a

  • 4 i

AVERAGE OL DURATIONS (Months) 1 ,,,,,~...-{M Fuel Load FuelLoad Controll"I Ready Ready \\ O 51 Fuel Load 5 g Ready g g Tatget W//2 2 Target 2 31 Targe} 25 ../ CY 1976 CY 1977 CY 1978 4

I AVERAGE PDA DURATIONS (Months) other Relat i Total Duration ali,e, i 25 19 20 WMj! 19 20 Target n N Target 17 Target 16 15 '~ 13 13 CY 1976 CY 1977 CY 1978

4 6 eam e ee m -m e -e-e ene --m**e . me ee .e.e= 9 i l 1 4 DETAILED BACKUP DATA FOR SCHEDULE PERF6RMANCE EVALUATION DECEMBER 31,1978 l i I i .). e a O O

l l .~ Duretion Evaluation - Major Causes For Delay (Durations in Months) I. LFA's issued in CY 1976 xaC f Federal Licensing Controlled Target Total Appilcation Duration Duration Major Causes For Delay (Months of Delay) Related Duration Duration Hartsville 1-4 12 19 Late appilcant responses (2)** 19 IF Extended hearings - heavily contested (5) Cherokee 1-3 13 22 Inadequate field data (8)* 14 14 Delay in initial decision by Board (2) l 17 16 Averages - 13 21 Averages Ol ~ Subtrected from Total Duration to obtain Federal Licensing Related and NRC Controlled Durations Subtracted from Total Duration to obtain NRC Controlled Duration e i 1 e 9 e 1 4 9 e

I II. LWA's issued in Cf 1977 NRC

  • Federal Licensing Controll Target Total Related Duration Duration Application Duration Duration Major Causes For Delar (Months of Delay)

WPP55 & 5 10 30 Awalting water quality permit 112)* 18 13 Court of Appeals Decision - Table 5-3 L 43** 1872 earthquake qI?** Board reque.. study on alternative L 3J energy sources Wolf Creek 14 30 Cnurt of Appeals decision - Table 5-3 1 53** 30 25 Cooling lake review (91 43) Hearing intervention ( 3)** 18 15 Phipps Bend 1 & 2 12 18 Late applicant responses I 3) 23 23 Marble Hill 1 & 2 55 23 Staf f impact Estended hearings - hearing intervention d 6) 22 19 1 Averages 13 25 ,_) Averages L Subtracted from Total Duration to obtain Federal Licensing Related and NRC Controlled Durations Subtracted from Total Duration to obtain.3C Controlled Duration.

.o l t III. LWs Issued in CT 1978 NRC rederal Licensing Controlled Ta rge t Total Application Durstfon Dura tion Major Causes For Delay Obaths of Delay) Related Duration Duration _ Yellow Creet I A 2 13 14 Late appilcant responses (2)** 14 12 Black Fox 1 & 2 15 31 Arpendia I (2) 20 20 Delay in obtaining water use permit (2)* fran city Appilcant delays affecting (g)* envirotunental hearing Reopened hearings on Table 5-3 redon (4) l 17 16 Averages 14 23 Averages l l O! Subtracted free Total Duration to obtain Federal Licensing Related and NRC Controlled Durations Subtracted from Total Duration to obtain MRC Controlled Duration 6 O e

l IV. CP's issued in CY 1976 5 l MRC Federal Licensing Controflev Related Duration Durat}3[, Total Major Causes For Delay (Months of Delay) Target Duration Duration 22 ['~5 Appilcation 14 i** 28 g Seismic probless 2, 28 i 20 Mark III containment problems d21** Clinton 1 & 2 Late appilcant responses 19 19 19 Mone 19 22 Palo Verde 1-3 22 (2) 22 Staff lepact 20 24 Callaway 1 & 2 (12)** 36 Applicant delay in resolving open issues (3) Extended hearings - heavily contested 36 Seabrook I & 2 22 22 26 Averages i 26 20 Averages Duration to obtain NRC Controlled Duration Subtracted from Total I I i 1 t .. = ~

V. CP's issued in CY 1971_ i NRC Federal Licensing Controlled Tar 9et Total Application Duration Duration Major Causes For Delay (Months of Delay) Related Duration Duration i 3 1 31 21 Wolf Creek 19 35 Staff impact Appendia I L3 i Table 5-3 1 40 ** Court of Appeals Decision Reopened hearing - State financial d4J* requirement Cooling lake review (2) Sterling 19 38 Staff impact 3 38 25 Appendix I Financial review - new applicants added L2 ** Late applicant responses f3)** Court of Appeals Decision - Table 5-J L3)** Impact of Seabrook decision on cooling 1,5)** towers Tyrone 17 44 Late appilcant responses (T)** 32 20 3 year delay in construction start (4)* (applicant requested schedule slip) Financial review - new applicants added (2)** ECCS reevaluation - calculational error (3)** Change from 2 units to 1 unitt environmental (8)* Impact O s-! Hartsville 1-4 18 29 Open GE55AR ltems (12) 29 29 i 8 St. Lucie 2 20 47 Delays due to intended dupiteation of Unit 1 ( 6) 47 45 Technical problem - stalled hurricane (12) Alternate site studies ( 4) ECCS model problems - calculational error ( 2)** Subtracted f rom Total Duration to obtain Federal Licensing Related and NRC Controlled Durations

    • Subtracted from Total Duration to obtain NRC Controlled Duration 9

.w M

.g a \\ =- V. CP's issued in CY 1977_ (Continued) l ? NRC Federal Licensing Controlled l Related Duration Duration Target Total _Appitcation Duration Duration Major Causes Fot Delay (Months of Delay) 1 12 ** 42 22 ltiver Eend I & 2 16 42 Appilcant 1elay in resolving open items l 4 Appendla 1 , 6, O Court of Appeals Decision a Table 5-3 1 t ECCS reevalustion - calculational error h 2 l" 35 18 Perry I 8 2 19 46 Appilcant dest e changes ( 11 p *" I 16,) Late appilcant responses ECC5 reevaluation - calculational error Il 1l" Cherokee 1-3 20 43 Review stretchout due to delay in need (23)* 20 20 for CP 34 26 Averages 19 40 Averages O I Duration to obtain Federal Licensing Related and NRC Controlled Durations Subtracted from Total Subtracted from Total Duration to obtain NRC Controlled Duration l e t I i e i t

-~ ~ --. VI. CP's Issued in CY 1918_ MDC Federal Licensing Controlled Target Total Appilcation Duration Duration Major Causes For Delay (Months of Delay) Related Duration Duration f 5)** 28 23 Tellow Creek 1 & 2 19 28 Late appilcant responses I Staff Impact Generic Issue (ALAB-444) respcases ) IdPP55 4 17 52 State requirements Ig acted financial ( 9)* 37 20 qualifications submittal 1872 earthquake IF;iu i Site change ,6 r* L 4i Appendix I 3;l* 41 IR WPP55 3 A 5 19 44 Major plant redesign by applicant f 2 I ACRS delay - seismic review 6)" ECCS model problem - calculational error i ,1 / * ** 3 1872 earthquake P Discovery of local faulting in excavation L liarris 1-4 20 76 Total project delay - appilcant financlel (12)* 39 27 problems Ite teslqn of coollag system - State required L9ll* ,16 Review reactivated - rereview required Resolution of hearing issues and re-L T,J solution of fault Appilcant delay insubmitting inforsetion (12)" on issues Fhipps Bend I & 2 19 26 Appilcant appeal on selsmology/ hydrology ( 6)" 26 20 i i Subtracted from Total Duration to obtain Federal Licensing Related and MRC Contm11ed Durations t " Subtracted from Total Duration to obtain MRC Controlled Duration I I t o .A

s 0 VI. CP's issued in Cf 1918 (Continued) MRC Federal Licensing Controlled Target Total A Duration Duration hjor Causes for Delay (Months of Delay) Related Duration Duration y lication 31 28 f krble 11111 1 & 2 19 31 lleavily contested hearings (7)* Antitrust review and financial ( 3)* qualifications - new co-applicant Remanded 401 certificate ( 2) I 34 23 Avereges 19 43 Averages I 6 i Subtracted from Total Duration to obtain Federal Licensing Related and NRC Controlled Durations Subtracted from Total Duration to obtain NRC Controlled Duration I i t e-

.~ r - l l, VII. OL's issued in CT 1976 4 NRC Time to Federal Licensing Controlled Appilcation Duration Duration Ready Ma. lor Causes For Delay (Months of Delay) Related Duration Duration Total Fuel Load jf l Target Beaver Valley 1 21 39 39 Construction delays - materials labor & (12)* 27 27 weather (s liigh energy line criteria - redesign ( 6) necessary Crystal River 3 40 70 69 Construction deferred - financial (12)* 39 39 problems late applicant responses (12)* Construction delay - repair of defective ( 7)* equipment High energy line criteria - redesign ( 6) necessary NOTE: FSAR docketed 40 months ahead of anticipated fuel load date St. Lucie 1 24 36 36 Analytical and design changes - ( 3)" 36 20 reevaluation of natural phenomena Design changes due to population growth ( 3)** estimate changes Not responsive to resolving open issues ( 9)" ECCS reevaluation - calculational error (1)" O' Salem I 39 59 59 Construction delay - labor problems. ( 8)* 43 43 late equipment delivery Design sodifications based on operating ( 8)* expertence and performance optimization - applicant initiated High energy line criteria - redesign ( 5) necessary NOTE: ISAR docketed 39 senths ahead of anticipated fuel load dates Duration to obtain Federal Licensing Related and NRC Contrd11ed Durations f Subtracted from Total Subtracted from Total Duration to obtain NRC Controlled Duration i i

I d

e _ l n l o oi rt ta Cnr 2 aou 3 NCD O gnn io si nt ea cr iu LD 6 ld 3 ae rt ea dlee FR seg ) a y yn r a l o so swdo e e st at aeai v D a n w n wiet A ) wyo yo vra d f di wdi 2e r e o wat eat rsu u eea iea t ad n s irr vrr i ;w i h v u e u n) n s t t esd rsd Utti n n n ra a (sn o o o wn

wn rad i

tice t t i C M

i

( ( tt nt nfid a nnd and a l u r aae l ae l d pl u l cd pcd pepc D 6 y pl u iu san 7 a il tll tn i d 9 l tpc i pc i en e 1 e i pn npn ncet l D nai uai uiho l Y u l wn o C r - nt 2nt 2 r o 3eo eo dd; t n F hn fhn f nel n f w ow oat e o s o ; eu C i d e dl tdl tdlf i e s tees i ees i ep s C u u it ue nt ue nt mde R s a nefg uefg ueoag N s C ul a l a l coa pd r d pd r dp l r d r dmae nmae nms e n i s o roov ooov ooaov a j icl a ccl a ccwt a a h e e d 't D M T S S e t n a o l i e t R a I / r I 1 g u V n D g d i n s d a i oo n e d tL e l a y 9 7 7 1 c l o eld 6 6 4 5 i o l mea L r t iue l TFR l n e a o u r C f e d C r e R o n F N f o i lt 9 7 7 1 n n y aa 6 6 4 5 i i d a a a t r t t ou b b er TD o o t o o n t t a l n n p o o i i d t t n a a n r r a o u u g i t D D t n a 0 9 0 1 e i g 3 3 3 r 4 l l t r u a a e aD t t k T o o c T T o d m m n o o e r r e f f w 2 t d d e 3 s e e b t t f c c y f s n r l I a a r r h o r i t i e C k t t n c s b b o t F e u u a t i M c s r w g S S l n e s a ^ i w v n r v e f p o l v p r a r A B C B A I i Il! 1I I s6kij, e 1

/* a i I Vill. DL's issued in CY 1977_ NRC Time to Federal Licensing Controlled g Target Total Fuel Load Appilcation Duration Duration Ready 3/ Ma. lor Causes For Delay (Months of Delay) Related Duration Duration i North Anna 1 23 55 55 Construction deferred - financial problems (12)* 17 17 Construction delays - repair of defective (18)* 7 equipment Labor problem (2?* 1 6 [* Not responsive to resolving open items I 2) NPSit problem liighly contested hearing I, il 84 84 Second unit of 2-unit plant; review was Cook 2 completed when appilcant was ready to load fuel; not included in duration averages Davis Besse 1 20 48 48 Construction delays (18)* 21 21 Late appilcant responses ( 9)* Farley 1 24 46 44 Construction delays - reduced need for (15)* 26 2G power; financial tate appilcant responses ( 5* Staff impacts [2 21 21 Averages 22 50 49 v' ; Averages Duration to obtain Federal Licensing *Ralated and NRC Controlled Durations Subtracted from Total If Months between docketing and plant ready for fuel loading

i g i IX. OL's issued in CT 1978 NRC ilme to Federal Licensing Controlled Appilcation Duration Duration Ready 11 Major Causes For Delay (Months of Delay) Related Duration Duration _ Target Total Fuel Load t 32 32 D 28 51 51 Core Protection Calculator (I2l* ,f Arkansas 2 Review suspended - construction (6J stretchout Construction delays,non-CPC (13)* Hatch 2 22 31 31 Construction delay - financial ( 2)* 22 22 ) pmblems Construction delays, other reasons (2)* Three Mlle Island 2 24 46 46 Co otruction delay - financial (12)* 34 28 prob bes late at:plicantresponses (6)** 29 21 Averages Averages - 25 43 43 1 O Subtracted from Total Duration to obtain Federal Licensing Related and NRC Controlled Durations Subtracted from Total Duration to obtain NRC Controlled Duration Months between docketing and plant ready for fuel loading If I I l 1 e l.

I. PDA's issued in CY 1976 l i I MC ei i Federal Licensing Eontrolled Target Total Application Duration Duration Major Causes For Delay (Months of Delay)

  • Related Duration Duration _

RESAR-35 12 17 Unacceptable RilR design - applicant appeals (5)" 17 12 l O Braun 12 17 Staf f igact (3) II IT 22 21 4)" SWE55AR-RESAR-41 14 22 Open RESAR ltems and $1W-9 interactions f l Containment design issues - appilcant appeals (2J Staff impact - policy development l, SWESSAR-CESSAR 11 22 Staff impact - confilcts with SWESSAR-RESARs (4) 22 20 S&W-CE interactions Late applicant responses - higher priority (2)** on SWE55AR-RESAR NOTE: This case is somewhat analogous to a second unit of a multi-unit OL appilcation. Applicant and staff efforts were simultaneous on large portions of this and SWE55AR-RESAR-41. Emphasis was put where appilcant wanted it. Thus, this case not included in our ti rai 5 O 19 17 13 19 Averages I Averages I Subtracted from Total Duration to obtain NRC Controlled Duration i O 9

7 e-

  • ~

e II. PDA's issued in CY 1977 i I NRC Federal Licensing Controlled Total Related Duration Duration t Application Duration Duration Major Causes For Delay (Months of Delay) Target l (3) 19 19 fluor 16 19 5taff lepact 18 13 SWE55AR-RESAR 35 10 18 None (9 " 25 13 GE55AR-251 14 25 Late appilcant responses ACRS delay (1 ECCS reevaluation - calculational error h 3 )** " W -238 M555 12 17 ECCS reevaluattop - calculational error (3)** 17 14 i 20 16 Averages } 13 20 Averages L I Subtracted from Totall Duration to obtain NRC Controlled Duration l. t = ~ _J,

l e* l. III. PDA's issued in CY 1978 l I i MRC I Target Total Federal Licensing Controlled l Application Duration Duration Major Causes For Delay (Months of Delay) Related Duration Duration BSAR-205 16 27 Applicant late in responding to staff (4)** 27 23 requests Staff lapact (F) RISAR-414 14 22 Espansion of review scope - computer (8) 22 22 based protection system i 25 23 Averages - 15 25 Averages t t I C Suhtracted free Total Duration to obtain MRC Controlled Duration i e e 0 W l q 3 _}}