Forwards IE Insp Rept 50-282/79-25 on 791006-10 & 800103.No Noncompliance Noted
ML19294B380
Person / Time
Site: Prairie Island Xcel Energy icon.png
Issue date: 01/26/1980
From: Fiorelli G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Gilberts D
NORTHERN STATES POWER CO.
Shared Package
ML19294B381 List:
References
NUDOCS 8002280268
Download: ML19294B380 (2)


See also: IR 05000282/1979025

Text

.

pa arcu

UNITED STATES

{'{

f_

., g

NUCLE AR REGULATORY COMMIS510N

[

T gl f o

REGloN lli

g

5

f

799 ROOSEVELT ROAD

,,

%,

Qg8

GLEN ELLYN, ILUNOIS 60137

.....

U$h 2 ' 1 Su

Docket No. 50-282

Northern States Power Company

ATTN:

Mr. Dennis E. Gilberts

Vice President

Power Production and

System Operations

414 Nicollet Mall

Minneapolis, MN

35401

Gentlemen:

This refers to the inspection conducted by Mr. K. D. Ward of this

office on October 6-10, 1979 and January 3, 1980, of activities at

Prairie Island Nuclear Generating Plant, Unit 1, authorized by NRC

Operating License No. DPR-42, and to the discussion of our findings

with Mr. A. Hunstad and others of your staff at the conclusion of the

inspection.

The enclosed copy of our inspection report identifies areas examined

during the inspection. Within these areas, the inspection consisted of

a selective examination of procedures and repre sentative records, obser-

vations, and interviews with personnel.

No items of noncompliance with NRC requirements were identified during

the course of this inspection.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part

2, Title 10, Code of Federal Regulations, a copy of this letter and the

enclosed inspection report will be placed in the NRC's Public Document

Room, except as follows. If this report contains information that you

or your contractors believe to be proprietary, you must apply in writing

to this office, within twenty days of your receipt of this letter,

to

withhold such information from public disclosure. The application must

include a full statement of the reasons for which the information is

considered proprietary, and should be prepared so that proprietary

information identified in the application is contained in an enclosure

to the application.

8 o o n 280;t63

.

Northern States Power

-2-

c5A

030

'

Company

We will gladly discuss any questions you have concerning this

inspection.

Sincerely,

/

  1. .

Y

Gaston Fiorelli, Chief

Reactor Construction and

Engineering Support Branch

Enclosure:

IE Inspection

Report No. 50-282/79-25

cc w/ encl:

Mr. F. P. Tierney, Jr.,

Plant Manager

Central Files

Reproduction Unit NRC 20b

PDR

Local PDR

NSIC

TIC

John W. Ferman, Ph.D.,

Nuclear Engineer, MPCA