| Site: | Perry |
| Issue date: | 01/09/1980 |
| From: | Fiorelli G NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III) |
| To: | Davidson D CLEVELAND ELECTRIC ILLUMINATING CO. |
| References | |
| NUDOCS 8001240298 | |
| Download: ML19291C371 (1) | |
Text
p* "8009 UNITED STATES k,
NUCLEAR REGULATORY COMMISSION O
+
o REGION lli f
799 ROOSEVELT ROAD 5
f g
cLEN ELLYN, ILLINOl$ 60137 JAN 9 1980 Docket No. 50-440 Docket No. 50-441 The Cleveland Electric Illuminating Company ATTN: Dalwyn R. Davidson Vice President - System Engineering and Construction Post Office Box 5000 Cleveland, OH 44101
_ Centlemen:
Thank you for your final report dated December 20, 1979, pursuant to 10 CFR 50.55(e) regarding inadequate compaction of Class "A" backfill around P45 System piping and settling of individual pipes below design elevations. We will complete our review of this matter during a future inspection.
Your cooperation with us is appreciated.
Sincerely, G. Fiorelli, Chief Reactor Construction and Engineering Support Branch cc:
Central Files Reproduction Unit NRC 20b PDR Local PDR NSIC TIC Harold W. Kohn, Power Siting Commission Mr. Daniel D. Wilt, Attorney 1793 005 O.g01240297