f(Q
(
[pa arcg
'o
UNITED STATES
E'
, , f[,'g
NUCLEAR REGULATORY COMMISSION
- '
'-' //
c
REGION lli
,
,
o
4
8
799 ROOSEVELT ROAD
7
'
$,
%o ' be ' ef'
GLEN E LLYN. ILLINOIS 60137
>
-
,
y ' 6 lE
j
a
,
,y
.
v,
,
.
k)
Docket No. 50-254
y
Docket No. 50-265
4
Commonwealth Edison Company
ATTN:
Mr. Cordell Reed
Vice President
Post Office Box 767
Chicago, IL 60690
Gentlemen:
This refers to the inspection conducted by Messrs. N. J. Chrissotimos
and S. G. DuPont of this office on September 1 through October 17, 1980,
of activities at the Quad-Cities Nuclear Power Station Units 1 and 2
authorized by NRC :perating Licenses No. DPR-29 and No. DPR-30 ond to
the discussion of our findings with Mr. N. J. Kalivianakis at the
conclusion of the inspection.
The enclueed copy of our inspection report identities areas examined
during the inspection. Within these areas, the inspection consisted
of a selective examination of procedures and representative 1 .ords,
observations, and interviews with personnel.
During this in pection, certain of your activities appeared to be in non-
compliance witu NRC requirements, as described in the enclosed Appendix A.
With respect to Appendix A we noted tha' you have corrected Items No. 2 and
3.
Consequently, no reply to these items of noncompliance is required and
we have no further questions regarding the at this time.
This notice is sent to you pursuant to the provisions of Section 2.201 of
the NRC's " Rules of Practice," Part 2, Title 10, Code of Federal Regulations.
Section 2.201 requires you to submit to this office within trenty days of
your receipt of this notice a written statement or explanation in reply,
including for each item of noncompliance:
(1) corrective action taken and
the results achieved; (2) corrective action to be taken tc avoid further
noncompliance; and (3) the date when full compliance will be achieved.
In accordance with Settion 2.790 of the a ^f t Rules of Practice," Part
2, Title 10, Code of Federal Regulations, a copy of this letter, the
8012180 M
.
S'
b..
.
Commonwealth Edison Company
-2-
enclosures, and your response to this letter will be ploced in the NRC's
Public Docmaent Room, except as follows.
If the enclosures contain in-
formation that you or your contractors believe to be proprietary, you
must apply in writing to this office, within twenty days of your receipt
of this letter, to withhold such information from public disclosure.
The application must include a full statement of the reasons for which
the information is considered proprietary, and should be prepared so that
proprietary information identified in the application is contained in an
enclosure to the application.
We will gl_Ily discuss any questions you have concerning this inspection.
SincereJy,
1
0 /
/
1(1 uv /
F. Heishman, Chief
Re:ctor Operations and
Nuclear Support Branch
Enclosures:
1.
Appendix A, Notice
oi Violation
2.
IE Inspection Report
No. 50-254/80-22 and
No. 50-265/80-24
cc w/ encl:
Mr. J. S. Able, Director
of Nuclear Licensing