UNITED ST ATES NUCLEAR REGULATORY COMMISSION
['.,
o W ASHINGTON, 0. C. 20555 2
1 ljwp/
sw j JAN 111979 Docket No.
50-502 Mr. Sol Burstein Executive Vice President Wisconsin Electric Power Company 231 West Michigan Street Milwaukee, Wisconsin 53201
Dear Mr. Burttein:
SUBJECT:
SCHEDULE FOR THE RADIOLOGICAL SAFETY REVIEW 0F HAVEN UNIT 1 This letter is in regard to the establishment of a schedule for the safety review of your application for a construction permit for your Haven Nuclear Plant Unit 1.
A summary of the more important milestones is provided as an Enclosure for your information and review.
It should be realized that the enclosed dates are target milestones which may require some changes as the review process proceeds. While we will not formally inform you of minor schedule changes, we will confirm, in writing, significant crianges to the schedule.
You should review the dates asso
.ed with the milestones that require your input and advise us as to whether you believe the dates ?re realistic or should be adjusted.
I suggest that a representative of your organization telephone Mr. Robert Capra, the Licensing Project Manager for tne Haven safety review, to discuss the schedule.
If, during the course of our review, you believe there is a need to appeal a staff position because of disagreement, this need should be brought to the staff's attention as early as possible so that the appro-uriate meeting can be arranged on a timely basis. A written request is 7 9 012 2 o lo g A
JAN 111979 Mr. Sol Burstein not necessary and all such requests should be initiated through our staff project manager assigned to the review of your application. This procedure is an informal one, designed to allow opportunity for applicants to discuss, with management, areas of disagreement in the case review.
- aly, k
noger S. Boy, Director Division of Project Management Office of Nuclear Reactor Regulation
Enclosure:
As Stated ces w/ enclosure:
See next page
Mr. Sol Burstein Mr. William Charles Hanley cc: Gerald Charnoff, Esq.
President, Safe Haven Ltd.
Shaw, Pittnan, Potts & Trowbridge P
- 0. Box 40 1800 M Street, N. W.
Washington, D. C.
20036 Konler, Wisconsin 53044
'4r. Thomas Galazen Rcbert H. Gorske, Esq.
Northern Thunder General Counsel Box 334 Wisconsin Electric Power Company Turtle Lake, Wisconsin 5488<
780 North Water Street Milwaukee, Wisconsin 53202 A. William Finke, Esq.
Senior Attorney Wisconsin Electric Power Company 331 West Michigan Street Milwaukee, Wisconsin 53201 Thomas A. Lockyear, Esq.
Assistant Chief Counsel Public Service Commission of Wisconsin Hill Farms State Office Building 4802 Sheboygan Avenue Madison, Wisconsin 53702 Mr. Richard L. Prosise Bureau of Legal Services Department of Natural Resources Box 7921 Madison, Wisconsin 53707 David Beckwith, Esq.
Foley & Lardner 777 East Wisconsin Avenue Milwaukee, Wisconsin 53202
ENCLOSURE MILESTONES FOR HAVEN SAFETY REVIEW Date Milestone First ro:.nd questions 7/18/78 Through 12/18/78 (completed) issued to applicant 11/9/78 Through 4/2/79 (partially Responses to first round complete) questions received Staff positions issued 2/2/79 Through 2/28/79 to applicant 4/2/79 Responses to staff positions re eived 8/1/79 Safety Evaluation Report issued 9/7/79 ACRS full committee meeting Safety Evaluation Supplement issued 11/14/79 Earliest Start of Rad / Safety Hearing 12/14/79 8/6/80 Prospective Decision Date